Guides / Checklist
How to Document a Factory's Condition on Handover Day
November 21, 2026
Sign a handover report on the day you receive the keys, with photos and meter readings attached. It takes half a day and it is the document you will want most at the end of the lease, when the landlord decides how much of the deposit to return. If you move equipment in first and check later, you cannot show what was already there.
When and who
When. Before any machines, racking or contractors enter. Do it in daylight. If it has rained in the last day, you can see leaks and wet patches.
Who. A landlord representative with authority to sign, and the plant manager or a person you appoint. Add a maintenance supervisor and, if you can, a person who speaks the landlord’s language. Both sides walk together and agree on each item as it is recorded.
How long. Allow half a day for a unit of 2,000 to 3,000 m². Bigger units take longer.
What the report should cover
| Section | What to record |
|---|---|
| Building structure | Walls, columns, roof sheets, gutters, leaks, cracks |
| Floor | Cracks, joints, patches, stains, level, drains |
| Doors, docks and gates | Roller doors, dock levellers, locks, gate motors |
| Office and toilets | Walls, ceilings, fixtures, air conditioning, sanitary ware |
| Electrical | Main board, distribution boards, lighting, earthing, transformer plate |
| Water and drainage | Taps, tanks, pumps, floor drains, grease traps |
| Fire protection | Alarm, extinguishers, hydrants, sprinklers, exit signs, test records |
| Cranes and lifting | Cranes, hoists, beams, load plates, latest safety inspection record |
| Yard and fencing | Road surface, drains, fence, lighting, gates |
| Keys and items | Number of keys, remotes, cards and fixtures supplied |
| Meters | Electricity and water readings with date and time |
How to take photos
Photos are the proof, so take them with care.
- Number every photo and list the numbers in the report with a short note, for example “photo 14: crack in the floor near column C4”.
- Wide shot first, then close. The wide shot shows where, the close shot shows what.
- Use a reference. A coin, a ruler or a tape measure in the frame shows the size of a crack.
- Keep the time stamp on the photos. Do not edit or compress them.
- Take video as you walk the unit, with a spoken running note.
- Share the full set. Both sides keep the same files, for example on a shared folder, and confirm in writing.
Meter readings and equipment
Record, with the date and the time:
- the electricity meter reading and the meter number
- the water meter reading and the meter number
- the transformer size on the plate, if you can see it
- the number of lights working and not working
- the state of the fire panel, the alarm and the hydrant pumps
Ask for the safety inspection record for cranes and lifting equipment if the unit has any. Do not use a crane until you have seen it and know who is responsible for its upkeep. See our guide to factories with overhead cranes.
Test, don’t just look
Some defects only show when you use the equipment.
- Open and close every door and dock.
- Turn on the lights in each zone.
- Run taps and flush toilets.
- Test the fire alarm if the landlord agrees.
- Switch the air conditioners and fans on.
- Check the drainage by running water at a floor drain.
- Walk the roof area from below after rain, or ask for roof photos.
Each item that fails goes on a defect list.
The defect list
Create a short table with three columns: the defect, who is responsible for the repair and the date it should be fixed. For example:
| Defect | Responsible | Date |
|---|---|---|
| Roof leak above bay 3 | Landlord | Before fit-out starts |
| Dock leveller 2 not working | Landlord | Within 30 days |
| Cracked floor joint near column C4 | Record only | None |
Defects marked “record only” are agreed as existing. Landlord repairs go with a date. Anything not listed is your risk later, so make the list complete.
Attach it to the lease
Write in the lease that the handover report forms part of it. Mention it in the clause on end-of-lease condition. Our guide on reinstatement at the end of a lease shows what that clause should say. If the building is not ready on the handover date, record what is unfinished and when it will be complete. Do not accept keys with “to be fixed later” and no date.
Looking for a factory now? Send my requirements
Keep it safe
Store the signed report, the photos and the meter reading sheet in more than one place. Keep a paper copy at the plant and a digital copy at head office. Repeat the process before you leave: do a similar walk with the landlord, compare it with the first report and settle differences in writing.
Day-one checklist
- Inspection before any equipment moves in
- Both sides present and signing
- All areas in the table above covered
- Numbered photos and a walk-through video
- Meter readings with date and time
- Defect list with responsible party and dates
- Report attached to the lease
- Copies stored by both sides
Common problems on handover day
The landlord’s representative cannot sign. Agree in advance who attends and what authority they have. If they cannot sign, ask for a written note that the report is accepted, and have the landlord countersign within a set number of days.
The unit is not clean or finished. Record it. If the lease says the unit is handed over empty and clean, include that in the defect list with a date for the fix.
The landlord’s agent is in a hurry. Do not rush. A walk of half a day is normal. Ask for a second session if you run out of time.
Language. Write the report in English and Vietnamese, or add a short note stating which version prevails. See the guide on bilingual lease contracts.
Shared areas. In a multi-tenant building, record the shared roof, toilets, gates and roads next to your unit as well, so that damage by neighbours is not charged to you.
Use the report during the lease
The report is not only for the end. Use it:
- when you make a repair claim, to show the item was already faulty
- when you add equipment, to show what was there before
- when ownership of the building changes, to show the condition to a new landlord
- when you negotiate the deposit return, to focus the talk on facts
Who pays for what you find
The report only helps if you agree what happens next. For each defect, decide whether the landlord repairs it before you start, repairs it within a period or you accept it as it is and the report records it. Write the answer next to the item. If the landlord agrees to pay for a repair you carry out yourself, put the amount or the method of calculating it in the report, and keep the invoices.
Get a shortlist
We visit each factory before it reaches your shortlist and send notes with photos, which gives you a head start on the day-one condition. Send your requirements and we reply within 24 business hours. Tenants pay nothing.
Frequently asked questions
What is a factory handover report?
It is a signed record of the building's condition, equipment and meter readings on the day the landlord hands over the keys. Both sides keep a copy, and it is attached to the lease.
Who should sign the handover report?
A person with authority from the landlord and a person from the tenant, ideally the plant manager. Both sign and date every page, and each side keeps the photos.
Why does the report affect my deposit?
At the end of the lease the landlord compares the unit to its starting condition. A clear day-one record helps show which damage was already there and which came from normal wear.
When should I do the inspection?
Before you move in any equipment and before fit-out starts. Do it in daylight and, if possible, after rain so you can see roof leaks.