Guides / Cost
How Much Cash Do You Need in Year One of a Leased Factory?
November 21, 2026
Year one of a leased factory needs more cash than twelve months of rent. A simple plan has four layers: the money paid at signing (deposit and advance rent), the money paid monthly (rent, fees and utilities), the one-off cost to make the unit work for your process (fit-out and power) and the working capital that your first orders need. The first two are easy to estimate from the lease. The last two come from quotes.
This guide shows how to build the plan. All numbers for rent are typical ranges seen on public listings, about US$4 to US$7 per m² per month before VAT. Replace them with the real offer.
Layer 1: cash at signing
| Item | Typical range | Notes |
|---|---|---|
| Deposit | 3 to 6 months of rent | Returned at lease end if the unit is handed back in good condition |
| Advance rent | One to three months | Paid on signing |
| Legal and adviser fees | Fixed quote from advisers | Lease review, registration |
The deposit is the largest single payment. It can be paid in cash or, with some landlords, replaced by a bank guarantee. See our guide to the lease deposit.
Layer 2: monthly running cost
Per month you pay:
- Rent on the production area.
- The park management fee per m².
- Power, water and wastewater at published rates.
- Any pass-through charge listed in the lease.
- VAT on rent and fees where it applies.
Worked rent example
Take a 2,000 m² unit at an example rent of US$5.50 per m² per month. This is an illustration, not a quote.
| Line | Amount |
|---|---|
| Monthly rent | US$11,000 |
| Rent for 12 months | US$132,000 |
| Deposit at 4 months | US$44,000 |
| Advance rent at 2 months | US$22,000 (part of the US$132,000, paid early) |
| Rent and deposit cash out in year one | US$176,000 |
The advance rent is a prepayment of rent you would pay anyway, so count it once. Year-one rent is US$132,000, and the deposit adds US$44,000 of cash that comes back at the end of the lease. At signing you pay the deposit and the advance rent together, US$66,000 in this example. Add the management fee and utilities on top.
If the landlord gives two months rent-free for fit-out, the rent for year one drops by US$22,000. That is why the rent-free period belongs in the plan from day one.
Layer 3: one-off cost to make the unit work
Fit-out
Offices, partitions, floor coating, compressed air, lighting, racking and ventilation. Get quotes from contractors for your own layout. The fit-out cost guide shows the line items.
Power
Compare your load in kVA with the transformer. If an upgrade is needed, agree cost, work and date in the lease. See transformer upgrade costs.
Fire approval
If your layout or process changes the use of the building, you may need an updated approval. Ask the park management board what is required.
Moving and installation
Transport, installation and commissioning of your machines. These come from your own forwarder and machine suppliers.
Layer 4: working capital
Rent is only part of what you need to start producing. Plan also for:
- Raw materials for the first orders, often bought before the first invoice.
- Wages for the staff you hire before output starts.
- Customer sampling and audit costs.
- Import duties and logistics on equipment and inputs.
These depend on your business. Ask your finance team to model them with realistic months of lead time.
A month-by-month shape
The shape of the cash curve matters as much as the total.
| Period | Main cash out |
|---|---|
| Month 0 | Deposit, advance rent, adviser fees |
| Months 1 to 3 | Fit-out, power work, hiring (rent may be free) |
| Months 3 to 5 | Machine install, trial runs, customer audit |
| Months 5 to 12 | Full rent, wages, materials, ramp-up |
Cash is lowest around month 4 to 6, when you pay everything and have little revenue. Check that your funding covers that low point.
Common planning mistakes
- Budgeting rent only, and forgetting the management fee and VAT.
- Using a fit-out figure from another plant instead of a quote for this layout.
- Forgetting the deposit is cash out on day one, even if it returns later.
- Assuming the transformer is big enough without checking.
- Missing the rent escalation in years two and three.
A short checklist
- Get the all-in monthly cost in writing: rent, fee, utilities, pass-through and VAT.
- List the deposit, advance rent and any bank guarantee fee.
- Collect three fit-out quotes.
- Confirm the power need and who pays for an upgrade.
- Add a reserve for fit-out and power overruns.
- Map the cash low point between months 4 and 6.
For the monthly figures, our cost guide shows how to compare two offers on one basis.
Looking for a factory now? Send my requirements
Two sample year-one paths
The two paths below use the same made-up unit: 2,000 m² at US$5.50 per m² per month. They are illustrations, not offers.
| Item | Path 1: light fit-out | Path 2: heavy fit-out |
|---|---|---|
| Rent-free months | 1 | 3 |
| Rent paid in year one | US$121,000 | US$99,000 |
| Deposit (4 months) | US$44,000 | US$44,000 |
| Fit-out | Small, from quotes | Large, from quotes |
| Power upgrade | Not needed | Needed, cost and date in lease |
| First full-output month | Month 3 | Month 6 |
Path 2 pays less rent in year one because of the longer rent-free period, but it reaches full output three months later. The cash you save on rent can be lost in delayed revenue. The right path depends on how quickly your customers wait for the first shipment.
What the landlord can do to lower your year-one cash
Landlords can adjust the shape of your payments without changing the total. Ask for:
- A rent-free period that starts at handover and runs through fit-out.
- A deposit in the form of a bank guarantee, if your company has a credit line. The bank charges a fee, so compare it with the cost of locking up cash.
- A staged deposit, where part is paid at signing and the rest at the start of production.
- Lower rent in year one and higher rent later, if your volumes ramp up. Check the total over the term. A step-up is not free money.
- Landlord-funded upgrades with the cost spread through the rent. See the guide to transformer upgrades.
Not every landlord agrees, and park developers use standard terms more often than private owners. Ask anyway, in writing, and let them decline.
Who should review the plan
Your finance lead owns the cash curve. Your plant manager owns the fit-out and power lines. A licensed adviser checks the lease and registration costs. Put the three in one room with the draft lease. Most year-one surprises come from a number that only one of the three had seen.
Review the plan at three points
A budget made before signing will be wrong in some lines. Review it when new facts arrive:
- After the shortlist visits. Replace rent estimates with written offers and add the management fee and pass-through.
- After contractor quotes. Replace the fit-out estimate with the real figure and update the cash low point.
- After the first three months of operation. Compare actual utilities and wages with the plan, and fix the model for year two.
Keep the first version of the plan. The gap between the first version and the real cost is the most useful number for your next site.
Get a shortlist
A budget is only as good as the offers behind it. Send your requirements and we check factories on site and send up to 5 that fit, with the numbers for each. We reply within 24 business hours and tenants pay nothing.
Frequently asked questions
What is the biggest cost in year one of a leased factory?
For most tenants it is rent over twelve months plus fit-out. The deposit is large but is returned at the end of the lease if the unit is handed back in good condition.
How many months of rent should I hold in cash?
Plan for the deposit and advance rent at signing, then rent for the months before output starts. A rent-free period during fit-out reduces this.
Should I include a contingency?
Yes. Fit-out and power work often move beyond the first quote. A reserve of a share of the fit-out budget, agreed with your finance team, is normal planning.