Who Pays When a Rented Factory Needs a Bigger Transformer?

November 21, 2026

A transformer upgrade is a matter of three decisions: how big the new capacity must be, who pays and by what date. Get all three into the lease before you sign. If you do not, you may pay rent on a unit that you cannot run at full load, or pay for an asset that stays with the landlord when you leave.

The cost of an upgrade depends on the size, the site and the utility. This guide does not give a price, because any figure we quoted would be a guess. It shows what makes up the bill and how to write the risk out of the contract.

Step 1: Size the load

Power is the check that most often changes a leasing decision. Do the sums before the site visit.

  1. List connected load. Add the rated kW of all machines, air compressors, cooling, lighting and office loads.
  2. Apply a demand factor. Not every machine runs at full power at once. A realistic factor depends on your process, and an electrical engineer should set it.
  3. Convert kW to kVA. Divide by the power factor. A common planning value is 0.8 to 0.9.
  4. Add a margin for growth and for the motor starting current.
  5. Compare with the plate. Standard transformer sizes step up in jumps, for example 250, 560 and 1,000 kVA, so a load just above one size means the next size up.

An example, using made-up numbers: connected load 600 kW, demand factor 0.7 gives 420 kW. Divided by a power factor of 0.9 this is about 467 kVA. With a margin you land above 500 kVA, so a 560 kVA unit is the first size that fits. This is a method, not an engineering design. Have it checked.

Our guide on factory power supply in kVA goes further on reading the transformer plate and on dedicated versus shared supply.

Step 2: Find out what the unit has

Ask the landlord for:

  • Transformer size in kVA and voltage.
  • Whether it serves only your unit or other tenants.
  • The last load record or electricity bill peak.
  • The age and condition, and the maintenance record.
  • Whether space exists for a larger unit or a second transformer.

Then compare against your load. A gap of a few percent can be managed with load planning. A large gap needs an upgrade.

What makes up the cost of an upgrade

The list below shows the items that appear in an upgrade. It is not a price list.

Item What it is
Transformer The unit itself, new or replacement
Medium-voltage equipment Switchgear, cables and protection on the supply side
Low-voltage panel changes Main distribution board, breakers and busbars
Civil works Foundation, enclosure or room, cable trench
Utility or park fees Connection or approval charges, where they apply
Engineering and testing Design, inspection and commissioning
Downtime Time without power during the switch

Each item has a cost and a lead time. Transformers and switchgear can be the long items, so ask the contractor for the lead time in writing.

Who pays: four common structures

Structure How it works Watch for
Landlord pays Included in the rent or a one-time landlord cost Make sure the date is in the lease
Tenant pays Tenant buys and installs, the asset stays Ask for ownership terms and a rent credit
Landlord builds, tenant repays Cost recovered through higher rent over the term Check the total over the term and what happens on early exit
Shared Costs split by an agreed ratio Define the ratio and what counts as a cost

Landlords are more willing to pay for an upgrade when the lease is long, because they recover the cost. A short lease raises the cost per month. You can use that: a longer term in return for a landlord-funded upgrade is a normal trade.

Clauses to add to the lease

  • Capacity guarantee. The landlord confirms the supply capacity in kVA at handover.
  • Completion date. The upgrade finishes by a stated date.
  • Remedy for delay. Rent is reduced or suspended for each day after that date. A rent-free period that starts only when power is ready is a clean way to do this. See our guide to the rent-free period.
  • Ownership. Who owns the transformer and what happens at the end.
  • Access. The utility or contractor can enter the site.
  • Approvals. Who applies to the utility and who bears the fee.

Looking for a factory now? Send my requirements

Timing and your move-in date

The upgrade often sits on the critical path. Machines cannot run on a transformer that is too small, and the utility may need weeks or months to approve and connect. If your move-in date is fixed by a customer, treat the upgrade like a construction project: ask for a written schedule and a named contractor.

Where speed matters most, a unit that already has enough capacity may cost more in rent but save months. Compare the extra rent with the cost of the delay.

Power costs after the upgrade

Capacity is one cost. The price of each kWh is another and depends on the tariff and the hours you run. Read our guide on electricity cost for factories to estimate the monthly bill.

Options when an upgrade is too slow or too costly

An upgrade is not the only answer. Before you commit, consider:

  • A different unit. A unit with spare capacity may cost more in rent but save months. Compare the monthly difference against the cost of the delay.
  • Load planning. Stagger start-up of large motors, add soft starters and correct the power factor. These steps reduce peak demand and can postpone an upgrade.
  • Phasing. Start with the machines that fit the existing supply and add the rest when the upgrade is complete.
  • A second transformer. If the site has space, a second unit is sometimes faster than replacing the first.
  • Generation on site. Rooftop solar can lower the grid demand for part of the day, but it needs the roof structure and the rules checked first. Treat it as an addition, not a substitute for a correct supply.

Each option has costs and approvals of its own. Ask an electrical engineer to compare them for your load.

What to check on the day of handover

When the work is done, do not accept the unit on the landlord’s word. Check:

  1. The new nameplate: kVA, voltage and manufacturer.
  2. Test and commissioning records from the contractor.
  3. The utility’s acceptance or connection letter.
  4. A meter reading at handover.
  5. The updated single-line diagram and panel schedule.
  6. A short written statement from the landlord that the capacity in the lease is available.

Keep these papers with the lease. They matter again when you reinstate the unit at the end, as described in our guide on reinstatement.

Questions for the landlord and the park

Send these in writing before you shortlist a unit:

  1. What is the transformer rating and is it dedicated to this unit?
  2. What was the highest demand recorded in the last twelve months?
  3. Is there room and permission to add capacity?
  4. Who supplies and approves the connection: the park, the utility or both?
  5. What is the usual time from order to energizing in this park?
  6. Has an upgrade been done for another tenant here, and can I speak to the contractor?

A park that has done upgrades before can answer these in a day. A landlord who cannot answer is telling you the time is uncertain.

Get a shortlist

Give us your connected load and shift pattern and we check the transformer, the supply and the upgrade options on each factory we visit. Send your requirements and we reply within 24 business hours. Tenants pay nothing.

Frequently asked questions

Who pays for a transformer upgrade in a leased factory?

It is a matter for negotiation. Common splits are the landlord pays, the tenant pays or the landlord builds it and recovers the cost through rent. Whatever you agree, put it in the lease with a completion date.

How long does a transformer upgrade take?

It depends on the size of the upgrade and on the park and the utility. Small changes can take weeks. A new transformer or a new connection can take several months, so ask for a written timeline before signing.

How do I know if the transformer is big enough?

Add up the rated power of your machines, apply a realistic demand factor, convert to kVA and add a margin. Compare the result with the kVA on the transformer plate, and ask a qualified electrical engineer to confirm.

Does the transformer stay with the building at the end of the lease?

Usually yes if the landlord owns it or it is fixed to the building. If you pay for it, ask for a clause that says who owns it and whether you get a credit.