How Many kVA Does Your Factory Need, and How Do You Check It?

November 21, 2026

Check three numbers before you lease: the transformer rating in kVA on its nameplate, the maximum load your own machines will draw, and whether the transformer serves only your unit. If the rating is at least 25% above your expected running load and the transformer is dedicated, the unit is safe on power. If not, ask what an upgrade takes before you go further.

Power is the check that most often changes a decision. A floor, a roof or a dock can be improved after you move in. A grid connection cannot be changed in a week.

kVA and kW are not the same

A transformer is rated in kVA, apparent power. Your machines use kW, real power. The link between them is the power factor:

kW = kVA × power factor

Most factories run at a power factor between 0.8 and 0.95. A 1,000 kVA transformer at 0.85 delivers about 850 kW. If you read a machine list in kW, divide by the power factor to get kVA. You can read more on the volt-ampere page.

Utilities in Vietnam commonly bill extra for a low power factor, often below 0.9. Ask the landlord whether the unit has power factor correction capacitors, and who looks after them.

How the supply reaches your unit

Most southern industrial parks bring medium voltage, commonly 22 kV, from a park substation to each building. A transformer at the unit steps it down to 380 V three-phase, which feeds your main distribution board. So there are four things to see on a visit:

  • the transformer itself, in a fenced bay or on a pad
  • the medium voltage switchgear and cables in front of it
  • the main distribution board inside the building
  • the electricity meter, and who reads it

Take photos of all four. Ask for the single-line diagram of the unit, which shows how they connect.

Reading the transformer nameplate

Every transformer carries a metal plate. Ask the landlord to let you read it and photograph it.

Nameplate item What it tells you
Rated power (kVA) The most the transformer is built to deliver. Common sizes run from 250 to 1,600 kVA.
Primary and secondary voltage Confirms the medium voltage side and the 380 V side your machines need.
Year of manufacture Older units lose efficiency and need more maintenance.
Cooling type Oil-filled or dry-type. Oil-filled units need a bund and fire protection around them.
Impedance (%) Affects voltage drop when large motors start.

If the plate is unreadable or the landlord cannot show it, treat the stated kVA as unverified.

Dedicated or shared power

Some units have their own transformer, meter and utility contract. Others take power from a transformer shared with neighbouring units, with sub-meters. Both work, but they differ in risk.

  • Dedicated: the capacity is yours. A neighbour cannot take it. Upgrades depend only on you and the landlord.
  • Shared: your usable capacity is whatever neighbours leave free. A new tenant next door can push the transformer to its limit.

Ask these questions for a shared supply:

  1. How many units share the transformer, and what is the total connected load?
  2. Is there a cap on my share, written in the lease?
  3. Who reads the sub-meter, and at what rate am I billed?
  4. Do I sign a contract with the utility, or do I pay through the landlord?

Estimate your own load

Do the estimate before you talk to landlords, so you can ask for the right size.

Step 1: list the connected load. Add up the rated kW of every machine, plus lighting, air conditioning, compressors and office equipment.

Step 2: apply a demand factor. Not everything runs at full load together. For many plants the running load is 60% to 80% of connected load. Use a higher figure if all machines run at the same time, such as injection moulding or heating lines.

Step 3: convert to kVA. Divide the running kW by the power factor.

Step 4: add headroom. Do not plan to run a transformer above about 80% of its rating for long periods. Divide by 0.8.

A worked example: a plant has 600 kW of connected load. Demand factor 0.7 gives 420 kW running. At a power factor of 0.85, that is about 495 kVA. With 80% maximum loading, the transformer should be about 620 kVA, so a 630 kVA unit fits and a 560 kVA unit does not.

Add the largest motors’ starting current to your notes. A large compressor or press starting up draws several times its running current for a moment, and a weak supply shows it as dips in voltage.

Plan for growth

If you expect to add lines in year two, size the supply for that, or choose a unit where there is space and park capacity for a second transformer. Moving later costs more than paying for headroom now.

Looking for a factory now? Send my requirements

What to ask the landlord and the park

  • What is the transformer rating, and can I see the nameplate?
  • Is the supply dedicated to this unit?
  • What is the connected load of the current or last tenant?
  • Does the park substation have spare capacity for an upgrade?
  • If I need more, how long does it take and who applies to the utility?
  • Who pays, and is the cost recovered through rent?
  • Is there a backup line or generator, and who owns it?

Frequent outages disrupt production more than a small transformer. Ask the park management how often power was cut in the last twelve months, and how long each cut lasted.

When the unit is too small

An upgrade means a larger transformer, new switchgear and a new agreement with the utility. It needs physical space, spare capacity upstream and approval. The timing can run from weeks for small changes to several months for a new connection. Our guide to transformer upgrade cost covers who pays and how to write it into the lease.

If an upgrade is likely, ask for these points in writing:

  • the landlord applies for it and builds it
  • a target completion date
  • a rent reduction or extension of the rent-free period for each month of delay

Do not forget the running cost

Capacity is one thing, the monthly bill is another. Production tariffs differ by time of day, and your shift pattern changes what you pay. Our guide to electricity cost for factories shows how to estimate a monthly bill. For the other site checks, use the ready-built factory checklist.

Backup power and power quality

Capacity is not the only power question. Ask how steady the supply is.

  • Outages. Ask the park management, not only the landlord, how many cuts happened in the last year and how long they lasted. Short cuts can ruin a moulding cycle or a batch of electronics.
  • Voltage dips. Sensitive equipment such as CNC controls, servo drives and test equipment can trip on a dip. Ask whether the park has had complaints.
  • Generator. Check whether the unit has a generator or a space and a foundation for one. Note the fuel storage rules and the noise limits in the park.
  • Backup feeds. Some parks supply from two lines. Ask if the unit can switch between them.

If your process cannot stop, price an uninterruptible supply for the control systems and a generator for the line before you compare rents.

Get a shortlist

Send us your machine list or your estimated kVA, and we will only show you units whose transformer fits, checked on site. Send your requirements and we reply within 24 business hours. Tenants pay nothing.

Frequently asked questions

What is the difference between kVA and kW?

kVA is the apparent power a transformer can deliver, kW is the real power your machines use. kW equals kVA times the power factor, so a 1,000 kVA transformer at a power factor of 0.85 gives about 850 kW.

How big a transformer does a small factory need?

It depends on the machines, not on floor area. Light assembly in 1,000 m² may run on a few hundred kVA, while injection moulding or machining of the same size can need 630 kVA or more. Add up your connected load before you ask landlords.

Is the transformer always dedicated to one unit?

No. Some units have their own transformer and meter, others share a transformer with neighbours. Ask for the single-line diagram and the meter arrangement, and get it written into the lease.

Can I add power after I sign the lease?

Sometimes. An upgrade needs space for a bigger transformer, spare capacity at the park substation and several weeks to months of work. Agree in the lease who applies, who pays and what happens to your rent during the wait.