How Do You Compare Shortlisted Factories on the Same Basis?

November 21, 2026

To compare factories for rent fairly, run every unit through two steps. First a gate: any unit that fails a must-have drops out. Then a score: the units that pass are rated on the same lines, with weights you set before you see the numbers. Add an all-in monthly cost and a risk line, and the winner is usually clear. This guide gives the matrix, a worked example and the traps to avoid.

Why a scorecard

After a visit trip, the last unit you saw and the owner you liked tend to win. A scorecard prevents that. It also gives you something to show your head office. The people who approve the lease were not on the trip, and they need to see why one unit beat the others. The approval pack guide shows where the scorecard goes in the pack.

Step 1: set the gate

Take the must-have lines from your brief. Each is a pass or fail:

Gate Pass condition (example)
Production area 2,500 m² or more of usable floor
Clear height 8 m or more under the lowest beam
Power 630 kVA or more available to you
Fire approval Valid for your intended use, or a clear path to it
Business line Allowed in the park, in writing
Handover Keys by your date
Land and building papers Complete and matching the unit

If a unit fails, mark it “out” and stop. A beautiful unit with 6 m height is not a candidate for a line that needs 8 m. See the requirements template for how to set the must-have list.

A unit that fails a gate by a small margin may still be a candidate if the owner can fix it before the lease starts, in writing. Treat that as a condition, not a pass.

Step 2: choose the lines and the weights

Score the units that pass. Use five to eight lines. Give each a weight so that the weights add up to 100. A sample set for a metal parts plant:

Line Weight What it measures
Fit to process 20 Layout, column spacing, floor, utilities
Power and utilities 15 Free kVA, upgrade time, water, wastewater
Papers and legal 20 Fire approval, land right, owner authority, mortgage
Location 15 Port distance, workforce, road, flood record
All-in cost 15 Monthly cost and one-off costs
Landlord terms 10 Escalation, rent-free, exit, repair duties
Risk 5 Neighbours, age, hidden defects

Set the weights before you open the offers. If you set them afterwards, you will tune them to the unit you already like. Share the weights with the team and agree.

Rate each line from 1 to 5, where 1 is poor and 5 is strong. Write down in one sentence why you gave each score, for example “Power 4: 630 kVA free, upgrade to 1,000 kVA possible in about 4 months, owner agrees in writing.”

Step 3: put all costs on one basis

Rent per m² compares badly. Use a monthly all-in cost for the area you need. Build it like this:

  1. Rent per m² x production area you will use
  2. Plus the management fee
  3. Plus any pass-through fees
  4. Plus VAT, if you compare after VAT
  5. Plus the monthly cost of one-off items, spread over the lease term

One-off items include fit-out, a power upgrade, a fire approval update, crane or dock work and moving costs. Divide each by the number of months of the lease. The rent cost guide lists the parts, and the hidden costs guide lists what often goes missing. For the year-one cash view, see the first-year budget.

Typical ranges seen on public listings for ready-built units inside southern parks are about US$4 to US$7 per m² per month. Use the range only to check that an offer is plausible. Your numbers come from the quotes.

Looking for a factory now? Send my requirements

A worked example

This example is made up to show the method. The figures do not describe real units.

Assume a plant needs 2,500 m² on a 5-year term. Three units pass the gate.

Item Unit A Unit B Unit C
Rent per m² per month US$5.50 US$4.80 US$6.20
Management fee per m² per month US$0.50 US$0.40 US$0.60
Monthly base (2,500 m²) US$15,000 US$13,000 US$17,000
One-off costs (fit-out, power, fire update) US$90,000 US$180,000 US$40,000
One-off spread over 60 months US$1,500 US$3,000 US$667
All-in monthly cost US$16,500 US$16,000 US$17,667

Unit B has the lowest rent but needs a transformer upgrade and a new fire approval, so its one-off costs are the highest. Over five years its advantage over A shrinks to US$500 a month, and it takes longer to open. Now the scores:

Line Weight A B C
Fit to process 20 4 4 5
Power and utilities 15 4 2 5
Papers and legal 20 4 3 4
Location 15 4 3 4
All-in cost 15 4 5 3
Landlord terms 10 3 4 3
Risk 5 4 2 4

Weighted score (score x weight, divided by 5, so the maximum is 100):

  • Unit A: (4x20 + 4x15 + 4x20 + 4x15 + 4x15 + 3x10 + 4x5) / 5 = 390 / 5 = 78
  • Unit B: (4x20 + 2x15 + 3x20 + 3x15 + 5x15 + 4x10 + 2x5) / 5 = 340 / 5 = 68
  • Unit C: (5x20 + 5x15 + 4x20 + 4x15 + 3x15 + 3x10 + 4x5) / 5 = 410 / 5 = 82

Unit C ranks first even though it has the highest rent, because it needs the least work and has the strongest power. Unit B, the cheapest on rent, ranks last. If your head office values lowest cost above all else, set the cost weight higher before you score, and note that you changed it and why.

Step 4: test the result

Before you decide, check that the scores are not an accident.

  • Change one weight. If the winner changes when you move cost from 15 to 25, the gap is small, so look at the terms again.
  • Look at the lowest score. A winner with a 2 on papers is not a winner until the papers are fixed.
  • Ask the engineer. Does the winner feel right to the person who runs the plant?
  • Re-ask the owners. Send each owner your all-in table and ask them to confirm or correct it.

Common mistakes

  1. Scoring before gating. A unit with a fatal flaw can still score well on other lines.
  2. Comparing rent per m² without checking which area it applies to. See gross and usable area.
  3. Ignoring one-off costs.
  4. Giving every line the same weight. Not everything matters equally.
  5. Scoring from memory. Score on site or on the same day.
  6. Letting one person score. Have two people score separately, then compare.

What the scorecard does not decide

A scorecard ranks units. It does not clear the papers. The top two units still go through a document check: land use rights, fire approval, the signer, mortgage and sublease status. Use the landlord due diligence guide and the site checklist. The scorecard is step five of the path in how to find a factory for rent in Vietnam.

Get a shortlist

We send each factory on a shortlist with the same fields, so you can drop them into a table like this one. Send your requirements and we reply within 24 business hours with a shortlist of up to 5 factories checked on site. Tenants pay nothing.

Frequently asked questions

How many factories should I compare?

Three to five. Fewer than three gives no real comparison. More than five makes the scoring slow and the differences small. Cut the long list with a pass or fail gate before you score.

Should rent carry the most weight?

Rarely. Rent is the easiest number to compare, so it tends to dominate. Power, papers and fit to the process decide whether the unit works at all, so score them first and weigh cost alongside them.

How do I score a unit that fails one must-have?

Do not score it. A must-have is a gate. If a unit fails one, drop it or write down what it would cost and take to fix, then score it with that fix included.

Can the same scorecard be used for different sites in different areas?

Yes. Keep the lines and weights fixed, and add location lines for ports, workforce and your customers. The point is to apply the same rules to every unit.