What Should a Head Office Approval Pack Contain?

November 21, 2026

A factory site selection report for head office should let a director decide from the first page and check from the last. It states the recommendation and the cost, compares three or four options on the same basis, shows the year-one cash, lists the risks with owners and gives a timeline to first shipment. This guide gives an outline you can copy, and explains what each part should say.

Who reads it

The reader is a director or a regional committee. They did not walk the sites. They know the business but not Vietnamese industrial leasing. They ask four questions:

  1. What do you recommend, and what does it cost?
  2. Why this unit and not the others?
  3. What can go wrong, and what is the cap on the downside?
  4. When do we ship?

Write for those questions. Everything else is support.

The outline

Section Length What goes in
1. Decision requested Half a page The unit, the lease term, the amount, the date of approval needed
2. Business need Half a page Why Vietnam, why now, volume and customer drivers
3. Requirements One page Must-haves and nice-to-haves with numbers
4. Options considered One to two pages Three to four units, key facts side by side
5. Scorecard and ranking One page Gate result, weighted scores and the reasons
6. Cost view One to two pages Monthly, year-one cash and multi-year total
7. Risks and mitigation One page Legal, power, fire, schedule, currency
8. Timeline One page Weeks to lease, registration, fit-out, first shipment
9. Next steps Half a page What happens after approval
Appendices As needed Papers, photos, offers, assumptions

Keep the main body short. Put the evidence in the appendices.

1. Decision requested

Open with the ask. For example: “Approve a five-year lease for a 2,800 m² ready-built factory in the Binh Duong area (now part of Ho Chi Minh City), with year-one cash of US$X and a first shipment in month Y.” One paragraph. If you need approval of a budget and of a signatory, say so.

Then give a one-line reason, for example: “It is the only option that passes all must-haves and has fire approval for our process.”

2. Business need

Describe what drives the lease: a customer contract, a capacity limit, a supply-chain diversification plan or a cost target. Keep to facts the reader can check. If the move is part of a wider shift, such as a China plus one strategy, say how this plant fits.

3. Requirements

Show the must-haves and nice-to-haves with numbers: area, clear height, floor load, power, crane, docks, location, dates and term. Use the same lines as the requirements template. A reader who sees the numbers understands why some options were removed.

4. Options considered

Give three or four units a short profile each. Put facts in a table:

Item Option A Option B Option C
Park and area
Production area
Clear height
Power available
Fire approval status
Rent, fee and VAT basis
Handover date
Owner and papers

Fill the table from written offers and the site visit, not from listings. If a number is an estimate, mark it. State how you found the options and why others were dropped. The path is described in how to find a factory for rent in Vietnam.

5. Scorecard and ranking

Show the gate result: which units passed the must-haves. Then show the weighted scores and the weights. Explain in one sentence why the winner won. The method is in the scorecard guide. If cost and score point to different units, say so and explain your choice.

6. Cost view

Directors read this section twice. Give three views:

Monthly cost. Rent, management fee and expected utilities for the area, before and after VAT.

Year-one cash. Deposit, advance rent, fit-out, power upgrade, moving, registration costs and first-month running costs. Use the first-year budget guide as a checklist.

Multi-year total. Total rent over the term with the escalation clause applied, plus one-off costs. If the lease is in US dollars, say so and note the currency risk, see lease currency in USD or VND.

Add a short comparison with other ways to get capacity, if the board will ask. Many will ask about renting versus buying or building.

State your assumptions in a list: area, term, escalation, exchange rate, power use. A reader can change an assumption and see the effect. Use only written offers for rent figures. Where you cite market levels, label them as typical ranges seen on public listings, which are about US$4 to US$7 per m² per month for ready-built units in southern parks, not as quotes.

Looking for a factory now? Send my requirements

7. Risks and mitigation

A risk table is stronger than a paragraph. This is an example of its form:

Risk Likelihood Effect Mitigation Owner
Fire approval does not cover our use Medium Start-up delayed Condition in the lease, adviser check before signing Legal
Power upgrade takes longer than planned Medium Delay in production Written date and remedy in lease Plant lead
Landlord cannot show the right to lease Low Lease void or disputed Paper check before the deposit Adviser
Rent escalation above plan Medium Higher cost Cap in the lease Finance
Registration takes longer Medium Late start File in parallel, early adviser Legal
Flood or access issue Low Interruption Site history check, insurance Plant lead

The ratings above are an example. Replace them with your own view for the unit. See the guides on landlord papers, lease clauses and insurance for items to put in the table. Say what you would do if the plan fails: the exit right, the break option, the sublease option.

8. Timeline

Show a week-by-week plan to first shipment, with the items that run in parallel. Use the phases in the setup timeline: lease, registration, fit-out and power, machines, hiring and trial runs. Mark the critical path, which is usually power, fire approval and registration. Give a date by which you need approval, and say what slips for each week of delay.

9. Next steps

List what happens on approval: signing the letter of intent, the legal review, the deposit, the registration file, contractor selection. Name an owner and a date for each step. A short list of ten lines is enough.

Appendices

Put the support here so that the main body stays short:

  • site visit notes and photos for each option
  • written offers from owners, with dates
  • the scorecard with scores and reasons
  • the cost model with assumptions
  • copies or summaries of papers, with the adviser’s note
  • the requirements brief
  • a glossary if the reader meets Vietnamese terms, see the glossary of listing terms

Style tips

  • Put the number before the story. “US$16,000 a month all-in” before “the landlord is flexible”.
  • Name the source of each number: offer dated, adviser note, site measurement.
  • Mark estimates as estimates.
  • Say what you do not know. A short list of open items builds trust.
  • Avoid adjectives. “The unit has 9 m clear height” beats “the unit is spacious”.
  • Do not copy a listing’s wording into the report. See how to read factory listings.

Before it goes up

Ask the plant lead to check the fit, finance to check the cash and a licensed Vietnamese adviser to check the papers and the registration path. Ask a colleague who did not join the search to read page one and say what the ask is. If they cannot, rewrite.

Get a shortlist

Our site notes, photos and open questions for each shortlisted factory are written so you can put them straight into the options section of your report. Send your requirements and we reply within 24 business hours with a shortlist of up to 5 factories checked on site. Tenants pay nothing.

Frequently asked questions

How long should a factory site selection report be?

Eight to twelve pages plus appendices. The first page should hold the recommendation, the cost and the decision you ask for. Detail goes in the appendices, so that a director can decide from page one and check from page ten.

What do directors look for in the report?

Total cost, start date, risk and what happens if the plan fails. They want to see the options compared on the same basis and a clear recommendation, not a list of factories.

Should I include rent quotes in the report?

Yes, as written offers from the owners with the date of each. Keep a note of what is included and what is not. Do not use listing prices or typical ranges as quotes.

Who should review the report before it goes up?

The plant lead for fit to process, finance for the cash view and a licensed Vietnamese adviser for papers and registration. Each reviews only their part, and you merge the results.