Does a Tenant in a Leased Factory Need an EIA in Vietnam?

November 8, 2026

A tenant in a leased factory needs an EIA (environmental impact assessment) only if the tenant’s own project falls in a higher-risk group under Vietnam’s environmental rules. A small assembly line usually does not. A plating, dyeing, tanning or large casting line often does. The landlord’s papers do not decide this for you. Your project is judged on its own process, its output and the waste it creates.

This guide explains the logic in plain terms, so you can ask the right questions before you sign. It is not legal advice. The lists and thresholds change, so confirm your case with a licensed environmental consultant or the park management board.

The rules behind it

The base law is the Law on Environmental Protection 2020 (Law 72/2020/QH14). It sorts investment projects into four groups by their risk of harming the environment. Government Decree 08/2022/ND-CP lists which projects fall in which group and sets the procedures. Decree 05/2025/ND-CP, issued in January 2025, amended parts of Decree 08/2022. Among other things it changed some thresholds and moved more approval work from the ministry to the provincial People’s Committees.

In short:

  • Higher-risk projects need an EIA report that a competent authority reviews and approves.
  • Medium and lower-risk projects usually need an environmental permit or a registration, not a full EIA.
  • The smallest or lowest-risk projects have the lightest duty or none.

Where your project lands depends on the exact lists and thresholds in force on the day you apply. Those lists name industries, capacity levels and the type of waste. Do not copy the answer from another factory, even one with a similar product.

Why a leased factory does not escape it

Many tenants assume that a ready-built unit in an industrial park is already “approved”. Two different things are mixed up here.

  1. The park. The park developer built the infrastructure under its own environmental approval. This covers the park’s roads, drains and central wastewater plant.
  2. Your project. Your company will be the investor of a new production project at that address. It has its own process, chemicals, wastewater and emissions. It needs its own classification.

The park papers help in one way: they usually set the limits for what the park wastewater plant accepts. If your wastewater is above those limits, you may need pre-treatment on site, and that is part of the assessment.

What decides your group

You cannot know your group from the product name alone. The factors that usually matter are:

Factor What the authority looks at
Industry Whether the process is on the list of higher-risk activities
Capacity Output per year compared with the threshold for that industry
Wastewater Volume per day and what it contains
Emissions Air emissions, dust, fumes, odour and noise
Waste Hazardous waste, its type and its quantity
Location Whether the site is inside an industrial park with a central treatment plant

Process steps often matter more than the product. An electronics assembly line is typically low risk, but the same plant with plating or a large paint line can move to a higher group. Furniture is mostly dry work, but a spray finishing line adds solvents and air treatment.

The usual order of steps

The order below is common. Your adviser will confirm the exact sequence for your case.

  1. Define the project. Write down the process flow, the machines, the chemicals, the daily water use and the headcount.
  2. Classify it. Ask a consultant to check the project against the current lists and decide the group.
  3. Check the park. Ask the park management board what the park requires from tenants and whether it will accept your wastewater.
  4. Prepare and file the documents. For an EIA this is the full report, prepared with a consultant, then reviewed by the competent authority. For lighter groups it is a permit application or a registration.
  5. Hold approval before operating. Do not plan a production start date until the document is in hand.

The authority that reviews your file depends on the project. Since the 2025 reorganisation of provinces, check which province your park now sits in. For example, parks in the old Binh Duong area are now in Ho Chi Minh City, and parks in the old Binh Phuoc area are in Dong Nai province. The review office may be new to the local consultants too, so allow time.

How timing can affect your lease

The EIA is a timing risk more than a cost risk for most tenants. A full report with a review can take months. If you sign a lease and start paying rent before you know your group, you may pay for an empty unit.

Practical protection:

  • Ask for a rent-free or reduced-rent period that starts at handover, not at lease signing. See our guide on the rent-free period in a factory lease.
  • Write a clause that links the lease start to the date the environmental document is issued, if your process is in a higher-risk group.
  • Ask for a short exclusivity period on the unit while you classify the project.
  • Confirm in the lease that the landlord will sign any letter the authority asks for, such as a confirmation of the site and its use.

Looking for a factory now? Send my requirements

Ask the landlord and the park these questions

  • Which environmental papers does the park hold, and can we see them?
  • Do you accept wastewater from [our process]? What are the limits and the minimum charge?
  • Has a similar tenant gone through the process in this park? How long did it take?
  • Are there processes this park does not allow? (See our note on which industries a park allows.)
  • Who handles hazardous waste collection in the park?

Landlords can often point you to consultants they have seen work well. Ask for two names and compare quotes.

What this article does not cover

The environmental permit that follows or replaces the EIA is a separate step, with its own timing. We cover it in the environmental permit guide. Fire approval is also separate, and it can block a start date as much as the EIA can. See fire safety approval.

For the law texts themselves, use the national legal database at vbpl.vn, and read them with a Vietnamese-speaking adviser, since official versions are in Vietnamese.

A short example of the thinking

Take three tenants who each want to lease 3,000 m² in the same park.

  • Tenant A assembles electronic modules. The process is dry, uses little water and produces packaging waste and small amounts of solder residue. The project is likely in a lower group, and the work is mostly about registration and waste handling.
  • Tenant B machines aluminium parts. It uses coolant, makes metal chips and may run a small anodising step. The coolant and the anodising are what the authority will look at, not the machining.
  • Tenant C dyes fabric. It uses a lot of water, chemicals and heat, and its wastewater is hard to treat. This type of project is far more likely to fall in a higher group and to face tight limits from the park.

The same size of building leads to three different paths. That is why you describe the process, not only the product, when you speak to the park or a consultant.

Common mistakes

  • Treating the landlord’s papers as yours. The landlord can show you the building permit and the park’s environmental approval. Neither is your project’s approval.
  • Changing the process after approval. A new chemical step, a bigger line or a new product can need an update to the approval. Raise it before you buy equipment.
  • Forgetting temporary wastewater. Start-up trials, cleaning and testing also create waste. Ask the park how it treats these flows.
  • Leaving hazardous waste to the last week. Set up a licensed collector before you start. The park may have a preferred one.
  • Asking only the landlord. The landlord may be honest and still wrong about what the authority will require. Ask the park board and a consultant.

Get a shortlist

If you have not yet picked a unit, we can screen factories for a park that accepts your process, before you spend money on a consultant. Send your requirements and include your process, chemicals and wastewater. We reply within 24 business hours. There is no fee for tenants.

Frequently asked questions

Does every tenant in a leased factory need an EIA?

No. Vietnamese rules sort investment projects into groups by size and pollution risk. Only projects in the higher-risk groups need a full EIA report. Lower-risk projects follow a lighter procedure or none. Your process, output and waste decide the group.

Who files the EIA, the landlord or the tenant?

The investor of the project files it. If you set up a company to run the factory, that is you, usually with a consultant. The park developer has its own environmental papers for the park, but they do not cover your production line.

Can I start production while the EIA is pending?

Treat the answer as no. Plan to hold the approval or permit before you operate, and ask the park management board what it requires at your stage. Starting without it can lead to fines or a stop order.

Does renting a ready-built factory shorten the EIA?

It can help, because the building and the park infrastructure already exist and the site is already zoned for industry. It does not remove your own project from the process. Your line, chemicals and waste still have to be assessed.

Looking for a factory now?

Send your requirements. We reply within 24 business hours and shortlist up to 5 checked factories. No fee for tenants.

Send my requirements