Which Clauses Matter Most in a Vietnam Factory Lease?

November 21, 2026

Read ten clauses first in any factory lease in Vietnam: the parties and premises, the term, rent and escalation, deposit, handover, repairs, permitted use, termination, hand-back and dispute resolution. These ten decide what the lease costs over its life and how hard it is to leave. The rest of the contract is mostly standard. This guide gives each clause in plain language, what to look for and what to ask.

This is general information, not legal advice. Have a licensed adviser in Vietnam review the final draft.

What the law gives you if the lease is silent

A lease is a contract, and the Civil Code 2015 sets default rules for leases that apply unless the parties agree something else. Knowing them tells you which clauses you can leave alone and which ones you must write yourself.

  • Condition and defects. The landlord must keep the premises in the condition agreed and suited to the purpose of the lease. It must repair defects, except small damage that custom puts on the tenant (Article 477).
  • Care and minor repairs. The tenant looks after the premises, maintains them and does minor repairs. The tenant pays for loss or damage, but not for natural wear (Article 479). The tenant may alter or improve the premises only with the landlord’s agreement.
  • Use. The tenant must use the premises for the agreed purpose. If not, the landlord may terminate and claim damages (Article 480).
  • Rent. The tenant pays on the agreed dates. Where rent is paid in periods, the landlord may terminate if the tenant misses three periods in a row, unless the lease says otherwise (Article 481).
  • Return. The tenant returns the premises in the condition it received them, apart from natural wear (Article 482).

When the landlord is a registered real estate business, the Law on Real Estate Business 2023 also lists the main contents of a lease of a building. They include the parties, the premises, price, payment schedule, handover, rights and duties, liability and penalties for breach, grounds for termination and how disputes are resolved (Article 46). A lease that skips any of these is a warning sign.

The ten clauses

# Clause What to look for What to ask
1 Parties and premises Exact legal names, the signer’s authority, the unit address, area and a plan Is the landlord the owner on the papers? Is the area gross or net?
2 Term Start date, end date, handover date, rent start date Does the term fit inside the land lease? See land lease term
3 Rent and escalation Currency, VAT, yearly increase, review dates Is the increase fixed or linked to an index? See rent escalation
4 Deposit and advance Months held, form (cash or bank guarantee), return date What deductions are allowed? See deposit guide
5 Handover Condition, utilities live, papers delivered, rent-free fit-out Who signs the condition report? See handover report
6 Repairs Structure, roof, utilities, minor repairs, response times Who pays for roof leaks and transformer faults?
7 Permitted use The business line, the fire safety use, hazardous materials Does the use match the park rules and the fire approval?
8 Termination Grounds, notice, cure period, break option What can each side do after a breach? See early termination
9 Hand-back Reinstatement, fixtures you may leave, inspection Which fit-out must be removed? See reinstatement
10 Disputes Court or arbitration, place, language, governing law Is there a step for talks before filing a claim?

Clauses that need more than a line

Term and options

The term should state four dates: signing, handover, rent start and end. If rent starts on signing but the landlord hands over three months later, you pay for space you cannot use. Link the rent start date to a signed handover report or to the date power is live. If you want a renewal option, write the notice period and how rent is set at renewal. A verbal promise to renew has no value.

Rent, VAT and currency

State the currency, whether rent is before VAT, and which exchange rate applies if you pay in Vietnamese dong. List what the rent covers: management fee, land charges, insurance and any shared services. Ask for the management fee as a separate line with a fixed amount or a clear rule for changes.

Repairs and utilities

Split the work in three groups: structure and roof, building systems and everything inside your fit-out. The default rules leave most structural repair with the landlord and minor repair with the tenant, but real leases often move more to the tenant. Write names, not words like “major” and “minor”. For the transformer, state who owns it, who maintains it and who pays for an upgrade.

Permitted use

Name the business line and the process in the lease, and make the landlord confirm that the building’s fire approval covers it. If your process later changes the use or the fire load, a new approval may be needed, and the lease should say who applies and who pays. See the fire safety approval guide for what to ask.

Termination and hand-back

Under the Civil Code a party may end a contract on its own only for a serious breach by the other side, or where the contract or the law allows it. Ending without such grounds can make the ending party the one in breach. So the lease should list the grounds clearly, set a notice period and give a time to fix a breach. Add a break option if your volumes are uncertain, and write its price.

Looking for a factory now? Send my requirements

Signing details that cause trouble later

  • Signatory. Check that the person signing for each side is the legal representative or holds a written authorisation.
  • Annexes. Attach the floor plan, the list of fixtures, the fee schedule, the park rules and the handover report. A lease that refers to papers you have not seen is not complete.
  • Copies and language. If you sign in two languages, write which one prevails. Have the Vietnamese version checked by someone who reads it, since that is the version most likely to be used with a local authority or court.
  • Landlord papers. Ask for the land use rights and construction papers before you sign. See landlord papers and due diligence.
  • Conditions before signing. If the lease depends on your investment registration or a permit, write the condition, a deadline and what happens to your deposit if it fails. See lease and investment registration.

A short review routine

  1. Read the ten clauses above in the draft and mark every blank, every “to be agreed” and every reference to a paper you have not seen.
  2. Compare dates: land lease expiry, lease end, rent start and handover.
  3. Total the cost over the full term, including increases, as in our factory rent cost guide.
  4. Send the marked draft to a licensed adviser with a list of the points you care about most.
  5. Ask the landlord to answer each point in writing, then ask for the changes in the contract itself.

Reading a landlord’s draft for risk

Landlord drafts favour the landlord, which is normal. Look for these patterns and ask for balance.

  • One-way rights. The landlord may enter, inspect, change fees or end the lease, but the tenant has no matching right. Ask for notice periods and reasons on both sides.
  • Open-ended costs. Phrases such as “other charges as notified” let costs grow without a cap. Ask for a list of charges and a rule for changing them.
  • Broad tenant duties. A duty to repair “all damage” can cover structural faults that are the landlord’s job under the default rules.
  • Short cure periods. A few days to fix a breach may be too short for a utility or permit problem.
  • Silent clauses. Missing rules on handover delay, power upgrade and loss of fire approval leave you with the default rules or none.

Do not try to rewrite the whole contract. Pick the five or six points that carry most of the money or risk, and ask for those changes in writing.

Who should read it

The plant manager reads for operations: area, power, crane, dock, handover date and fit-out rules. Finance reads for rent, deposit, increases and tax. A licensed adviser in Vietnam reads for validity, the land and building papers, and the dispute clause. If one of the three skips the review, the lease has a gap that someone will find later.

Get a shortlist

We check the factory, the landlord’s papers and the main terms before a unit reaches your shortlist, so you read a lease for a building that is already screened. Send your requirements and we reply within 24 business hours. Tenants pay nothing for the search.

Frequently asked questions

Can I use my own lease template in Vietnam?

Often yes, but the landlord usually sends its own form first, and park developers may be required to use standard forms. Compare any draft against the ten clauses in this guide and ask a licensed adviser to review it before you sign.

What applies if the lease says nothing about repairs?

The Civil Code sets default rules: the landlord keeps the premises in the agreed condition and repairs defects, and the tenant maintains the premises and does minor repairs. A written lease can change this split, so state it clearly.

Should the lease be signed by the foreign parent company or the Vietnam entity?

The tenant is normally the Vietnam-registered company that will run the factory, because the address on its registration must match the lease. Confirm the structure with your licensing adviser before signing.

Is a bilingual lease required?

No rule in this guide requires it, but it is common when the manager reading the contract does not read Vietnamese. Agree in the lease which language version prevails if the two differ.