Does the Factory Have Fire Approval? How to Check Before You Sign

November 18, 2026

Ask the landlord for two documents before you sign: the fire prevention design approval and the acceptance record for the fire systems actually installed. Then check that the use stated in them matches what you plan to do. A building approved as a warehouse can take months to approve as a paint shop, and you cannot operate legally until it does.

Fire safety is a legal condition for running a factory in Vietnam. It also affects insurance and your workers’ safety. The rules have changed in recent years, so confirm the current procedure with the authority or a licensed consultant. This guide tells you what to ask, not what the law requires in your exact case.

Two stages: approval and acceptance

In Vietnam a building with fire safety requirements goes through a design stage and a completion stage. The words used locally are thẩm duyệt for approval of the fire prevention design and nghiệm thu for acceptance tests of the installed systems. The fire prevention and rescue police unit of the local province or city handles them.

Stage What it proves What to ask to see
Design approval The fire design met the rules for the planned use The approval document and the approved drawings
Acceptance The systems were installed as approved and tested The acceptance record and test reports

A factory with approval but no acceptance is not finished in the fire authority’s eyes. A factory with acceptance only for part of the building leaves the rest open to question.

What to check against the real building

Documents are one thing, the building is another. Walk the unit with the papers in hand.

  • Approved use. Does the stated use fit your process? Storage, assembly, machining, painting and chemical handling are treated differently.
  • Area and floors. Does the approved area match the building? An extra mezzanine or a new office block may have been added later.
  • Fire compartments and walls. Are the fire walls, doors and openings as in the drawings?
  • Alarm and detection. Is there a fire alarm panel, with detectors and manual call points, and do they work?
  • Sprinklers and hydrants. Check pump room, tank, pipework and hydrants. Ask when they were last tested.
  • Extinguishers and signage. Extinguishers should be in date, and exit signs and emergency lights should work.
  • Exits and routes. Count exits and measure widths. Make sure racking or stock does not block them.
  • Fire access. The site needs a route for fire engines. Check the park roads and the building perimeter.

When your process changes the answer

Your plan may differ from the last tenant’s. Think about these changes.

  1. Higher fire load. Plastics, foam, rubber, paper, packaging and wood burn faster than metal parts.
  2. High-bay storage. Tall racking can need in-rack sprinklers or a different system.
  3. Mezzanines and new partitions. These can alter the fire compartments and the escape routes.
  4. Hazardous goods. Paint, solvents, gas cylinders and chemicals have their own storage rules.
  5. Heat or sparks. Welding, hot work and drying ovens need controls.

If any of these apply, speak to a licensed fire consultant before you commit to the building. Ask whether a new design approval is needed and how long it takes. Our guide to fire approval and change of use covers this case in more detail.

Who does what in the lease

The lease should answer these questions in plain words.

  • Does the landlord confirm the building has valid fire approval and acceptance for the agreed use?
  • If the tenant’s use needs a new approval, who applies, who pays and what is the deadline?
  • If approval is refused, can the tenant leave without penalty and get the deposit back?
  • Who maintains the alarm, sprinkler and hydrant systems, and who pays for yearly testing?
  • Does the landlord carry out any fire works that the authority requires?

A tenant who signs without these points can end up paying rent for a building they cannot open.

Insurers ask about fire protection, and a gap between the approved use and the real use can cause trouble in a claim. See our guide to insurance for tenants for the questions to ask.

Looking for a factory now? Send my requirements

Papers that go together

Fire approval is one of several documents. Land use rights, the construction permit and the park’s rules also matter. Read our due diligence guide and the ready-built factory checklist to cover them in the same visit.

A short list for your visit

  1. Ask for the design approval and acceptance records, with dates.
  2. Compare the approved use and area with the real building.
  3. Test the alarm and look at the sprinkler pump and tank.
  4. Check exits, extinguishers and emergency lights.
  5. Write down every gap and ask the landlord to fix it or state who will.
  6. Ask a licensed consultant if your process needs a new approval.

Common problems we see on checklists

These gaps come up often when a tenant compares a building with its papers.

  • Missing acceptance. The design was approved, but no acceptance record exists for the installed systems. The landlord needs to complete it, and it can take months.
  • Changed layout. Offices, mezzanines or partitions were added by an earlier tenant without updating the approval.
  • Expired or stale equipment. Extinguishers out of date, a dead alarm panel, a sprinkler pump that has not been run.
  • Blocked exits. Stock stacked in front of exit doors and on escape routes.
  • Wrong class of use. The papers say storage, but the unit was used for production.

Each gap is a negotiation point. Ask the landlord to fix it before handover, to confirm the fix in writing and to promise a refund of rent or a right to leave if the authority refuses your use.

Who to ask

For the final answer on your case, ask the fire prevention and rescue unit that covers the park, or a licensed fire consultant. The park management board often knows the local procedure and can tell you how long approvals have taken for other tenants. We do not give legal advice, and rules change, so get the current requirements confirmed before you sign.

Fire safety during fit-out

Your own works can break the approval. Offices built inside the hall, partitions, mezzanines, racking and new machine lines change escape distances and the way smoke and fire spread. Before work starts, show the layout to the landlord and ask whether the approval covers it. For larger changes, ask a licensed consultant to check the layout against the approved drawings, and whether the authority must see it before you open.

Keep a file with the approval, the acceptance record, test reports, training records and drill logs. The authority and your insurer can ask for them, and a new owner or tenant will want to see them later.

Get a shortlist

We ask for the fire approval and acceptance papers when we visit a factory, and note any gap before the unit goes on your shortlist. Send your requirements and tell us your process, so we can flag units where a change of use could be an issue. We reply within 24 business hours. Tenants pay nothing.

Frequently asked questions

What does PCCC mean?

PCCC is the Vietnamese abbreviation for fire prevention and fighting. In a factory lease it refers to the fire safety design approval, the acceptance of the installed systems and the ongoing fire safety compliance of the building.

Which documents should I ask the landlord for?

Ask for the fire prevention design approval, the acceptance record for the installed systems, the approved use stated in them, and any later changes. Check that the approval matches the building as it stands today.

Do I need a new approval if I change how the building is used?

Possibly. A different process, a higher fire load, new mezzanines, a paint line or storage of hazardous goods can mean the approval no longer fits. Ask the fire authority or a licensed fire consultant before you fit out.

Who pays for a fire approval update?

It depends on the lease. In practice the tenant often applies and pays when the change comes from the tenant's process. Agree this in writing before you sign, together with a deadline and what happens if the approval is refused.