Guides / Legal
When Does Your Process Need a New Fire Approval?
November 21, 2026
You need a new or updated fire approval whenever your use of a leased factory differs from the use the building was approved for, or when your works change the fire risk. A move from warehouse to production, a new mezzanine, a paint line or high racking can all do it. The approval for the building does not travel with your process. Treat it as a gate on your start date, not a formality.
This guide is general information, not legal advice. Fire rules are strict, and the fire authority has the final say in each case. Confirm your plan with a licensed fire consultant and the competent fire authority before you commit.
The rules in short
Vietnam’s fire law was replaced recently. The Law on Fire Prevention, Fighting, Rescue and Salvage (Law 55/2024/QH15) took effect on 1 July 2025, with Decree 105/2025/ND-CP giving the detail from the same date. The decree includes a list of building types whose fire safety design must be reviewed. As the decree reads, a building in that list must go through design review when it is designed, renovated or when its use changes. Factories with production or storage above stated size or risk levels are typically in scope, but the thresholds sit in the annex, so ask your consultant to check your building.
The usual stages are:
- Design review (appraisal) of the fire safety design. Done before works start for buildings in scope.
- Works carried out to the approved design.
- Acceptance of the fire systems before the building or the changed part is put to use.
For the building papers you should already hold, see factory fire safety approval.
What counts as a change of use
Fire rules look at what happens in the building and how much can burn. A change of use is wider than a change of the company name or product.
| Change | Why it matters |
|---|---|
| Warehouse to production | Machines, heat, electrical load and staff numbers rise |
| Light assembly to a line with solvents, paint, adhesives or foam | Fire load and ventilation needs rise sharply |
| Adding a mezzanine or second floor | New floor area, exits and travel distance |
| Higher racking or denser storage | Sprinkler design and fire load change |
| Storing batteries, plastics, chemicals or packaging in bulk | Fire hazard class can change |
| Adding offices, canteens or dormitory space in the unit | Mixed use with different exit and separation rules |
| Cutting new doors, walls or openings | Fire compartment and exit routes change |
| Changing sprinkler, alarm or smoke exhaust layout | The approved system no longer matches the building |
Even smaller steps, such as moving a fire door or closing a corridor with new racking, can break the approved plan. A change that is small to you may count as a change of design to the authority.
Why tenants get caught
The most common story goes like this. The tenant signs for a unit used as a warehouse by the last occupant. The papers show approval for storage. The tenant installs a production line, a mezzanine and extra racking. At the first inspection or when an insurer asks for papers, the approved use does not match the real use. Work stops until a new approval is in place.
Avoid it by running the fire check before you sign, using the facts of your own process:
- What is the approved use on the fire papers?
- What is your use, with materials, quantities and heights?
- Which gaps need a new design or system?
- How long and how much will it cost?
Who does what
| Step | Usually done by |
|---|---|
| Collect the existing fire approval and acceptance papers | Landlord provides, tenant checks |
| Describe the new use and layout | Tenant, with a design consultant |
| Prepare the design documents | Licensed fire design firm hired by the tenant |
| Landlord consent to works | Landlord, in writing |
| Submit for review | Investor of the change, often the tenant |
| Build the fire works | Tenant’s contractor, to the approved design |
| Acceptance before use | Tenant, with the competent authority |
If the park has its own fire team or rules, ask how it fits with the authority’s role. The fire authority is part of the police system, and the office you deal with depends on the project and location. After the 2025 province changes, check the right office for your park.
Lease clauses to write
- Representations. The landlord confirms the building has valid fire approval and acceptance for the stated use, and gives copies.
- Change of use. The landlord agrees not to unreasonably refuse consent to works needed for the tenant’s process.
- Cost split. The lease says who pays for design, new systems and fees. For works that improve the landlord’s building, ask for a share or rent credit.
- Timing. The lease start or full rent depends on the fire approval for the tenant’s use. See rent-free periods.
- Exit. If the approval is refused for reasons beyond your control, you can end the lease with a refund of the deposit and agreed costs.
- Handback. Which fire installations stay and which you remove. See reinstatement at lease end.
Looking for a factory now? Send my requirements
Checks before you pick a unit
- Ask the landlord for the fire design approval and acceptance documents and read the approved use.
- Walk the unit with your layout and mark exits, storage heights, mezzanines and process areas.
- Ask the fire consultant for an early opinion on the gap between the approved use and your plan. A short written opinion costs little.
- Check whether sprinklers exist and cover your storage height.
- Ask your insurer which fire documents it needs.
If you plan a mezzanine, read mezzanine permits in a leased factory too, since fire approval and construction rules work together.
When to speak to the authority
Talk to the fire authority or a licensed fire consultant before you finish the layout. Come with drawings, a list of materials and the quantities stored. A short meeting can tell you whether a full design review is needed, what documents to prepare and which systems are likely. Take notes, and ask for any guidance in writing.
Typical fire questions by process
The answers depend on the building and the authority, but these patterns come up often.
- Plastics and foam. Large quantities of plastic raw material and foam burn fast and give off heavy smoke. Expect questions about storage height, sprinklers and separation.
- Wood and furniture. Dust, finishing materials and drying areas raise the fire load. Dust collection and electrical safety matter.
- Paint and coating. Solvents, spray booths and ovens bring extra rules on ventilation, ignition sources and storage of flammable liquids.
- Batteries. Charging areas and stored cells need separate planning. Ask the consultant about it early.
- Food and cold storage. Insulation panels and refrigeration plants bring their own fire points.
- Electronics assembly. Lower fire load, but high electrical density and sometimes chemicals for cleaning.
Tell the consultant what your plant will really store and use. A fair description now is cheaper than a redesign later.
Documents to collect and keep
- Fire design approval and acceptance papers for the building
- Your own layout drawings with exits and storage areas marked
- Material list with quantities and storage heights
- Equipment list with electrical loads
- Any insurer’s requirements
- Records of inspections and drills
Keep them in one folder, in the form your authority and insurer accept. They are the first thing asked for at an inspection.
Get a shortlist
We check the fire approval papers on site for each unit and note the approved use, so you can compare it with your plan before you visit again. Send your requirements with your process and storage needs. We reply within 24 business hours. Tenants pay nothing.
Frequently asked questions
Does the fire approval of the building cover any tenant?
No. The approval covers the use and design that was reviewed. If your process, storage or layout changes the use or the fire risk, you may need an updated approval before you operate.
Which changes usually trigger a new fire review?
Changing the main use (for example from warehouse to production), adding a mezzanine, adding flammable materials or processes, raising storage height or changing exits and fire systems. Ask the fire authority for your case.
Who applies for the new approval, landlord or tenant?
It depends on the lease and on who is the investor of the change. Often the tenant applies for its own works, with the landlord's consent and documents. Write the split in the lease.
How long does a fire design review take?
It varies by authority and by project. Plan for weeks to a few months, and do not set a production start date until the approval and acceptance are in hand.
Looking for a factory now?
Send your requirements. We reply within 24 business hours and shortlist up to 5 checked factories. No fee for tenants.
Send my requirements