Which Fit-Out Works in a Leased Factory Need a Permit?

November 5, 2026

Fit-out works that change the structure, add floor area or alter the fire layout usually need more than a signature from the landlord. They may need a construction permit or an exemption confirmed by the authority, a design review and a fire approval. Light work that leaves the structure and exits alone, such as movable partitions and racking, is usually simpler. The line between the two is not obvious, so ask before you build.

This guide is general information, not legal advice. Construction rules were amended in recent years and local practice varies, so confirm your plan with a licensed adviser, the park management board and the local construction authority.

The rules in short

Construction in Vietnam is governed by the Law on Construction (Law 50/2014/QH13, amended by Law 62/2020/QH14), with decrees and local rules that fill in the detail. The law lists which works need a construction permit and which are exempt. Some works are exempt, and the exemptions have conditions. Industrial park works can be treated differently if the park has an approved detailed plan and the design has been reviewed, but the exact conditions sit in the current decrees. Do not assume an exemption applies to your unit. Ask the authority.

Three separate checks apply to most meaningful fit-out:

  1. Construction side. Is a permit needed, or is the work exempt? Is the design reviewed? Is the work notified?
  2. Fire side. Does the change affect fire compartments, exits, fire load or fire systems? If so, you may need a fire design review. See fire approval for change of use.
  3. Landlord and park side. Does the lease allow it, and does the park consider it a change that needs its own approval?

Typical fit-out works and the likely route

The table shows a general pattern. Your case may differ.

Work Typical route
Painting, lighting, movable racking Landlord notice. Usually no permit
Movable partitions and office pods Landlord consent. Check fire exits
Fixed internal walls and offices Landlord consent. Check with authority and fire rules
Epoxy floor coating Landlord consent. Check slab condition first
Machine foundations and pits Landlord consent, structural check, possible design review
Mezzanine floor Landlord consent, structural design, fire check and likely permit or design review
New overhead crane Landlord consent, structural check of columns and beams, design review
Roof openings, skylights, stacks, solar Landlord consent, structural and waterproofing check, possible permit
New external extension or canopy Permit or confirmed exemption, landlord and park approval
New dock doors or wall openings Landlord consent, structural check, fire check
Cleanroom build Structural, fire, ventilation and electrical checks. See cleanroom-ready factories

If your work is in the middle of the table, ask your design consultant to write a short route note for each item, and send it to the authority for comment.

Why a mezzanine is more than a floor

A mezzanine looks simple. In practice, it adds:

  • Load. The slab and the columns must carry the new floor and its use. See factory floor load capacity.
  • Floor area. It can change the building area and the tax or fee base. It may affect density limits in the park’s plan.
  • Fire. It changes exits, travel distance, sprinkler coverage and smoke control.
  • Height. It cuts the clear height under and above it. See clear height.
  • Insurance. Insurers ask for approved drawings of any structural addition.

Do not rely on a contractor’s word that it is “only a steel platform”. Authorities and insurers look at the function, the area and the people who will work on it.

The usual order of steps

  1. Ask the landlord for the as-built drawings, the structural limits and the fire approval documents.
  2. Hire a design firm to prepare the layout, the structural design and the fire design.
  3. Send the plan to the landlord for written consent, with a clear list of what will change.
  4. Ask the park and the authority which route applies: permit, exemption with notice, design review or none.
  5. Apply for what is needed. Allow time for review. Do not start works early.
  6. Build to the approved design, with a licensed contractor.
  7. Complete acceptance steps, including fire acceptance where needed.
  8. Record the works in a note to the landlord with as-built drawings.

Starting before steps 3 to 5 is the usual cause of stop orders.

Looking for a factory now? Send my requirements

Lease clauses to agree

  • Pre-approved works. A schedule of fit-out works the landlord approves now, with drawings, so you do not wait later.
  • Consent standard. The landlord will not unreasonably refuse or delay consent, and answers within a set number of days.
  • Cost and ownership. Who pays, who owns the work and whether it counts as a tenant fixture.
  • Cooperation. The landlord signs any document the authority asks for, such as an owner’s consent letter.
  • Permit risk. If a permit or approval is refused, the tenant can adjust the plan without penalty.
  • Removal. What you remove at the end and what you leave. See reinstatement at the end of the lease.
  • Rent-free for fit-out. A rent-free window that covers the approval time. See rent-free periods.

Budget for time, not only money

Fit-out budgets focus on materials and labour. Approval time often matters more. A mezzanine needs design, consent, review and construction in sequence. Even with no delay, that takes weeks. Build the time into your start date. Our guide to factory fit-out cost helps you plan line items, and the timeline from search to production shows where fit-out sits.

Questions for the authority

When you meet the park board or the construction authority, bring drawings and ask:

  • Is this work exempt from a permit, or does it need one?
  • If exempt, what notice or design review is required?
  • Which office handles it for this park, given the 2025 province and ward changes?
  • What documents does the landlord need to provide?
  • What fire approval step applies?
  • What happens if we change the layout during works?

Note the answers, the date and the officer’s name, and ask for a written reply where you can.

Using the landlord’s own design data

If the landlord or the park developer has the structural design of the building, ask for the relevant sheets. The columns, beams, slab and roof were designed for stated loads, and your consultant will start from these numbers. Without them, a consultant must survey and test, which takes time and money. Landlords that keep good records save you weeks.

Common mistakes with fit-out

  • Building first, asking later. The usual cause of stop orders and fines.
  • Relying on a contractor’s view alone. Contractors build. A design firm and the authority decide what is needed.
  • Forgetting the roof. Stacks, ducts and solar panels add load and holes, and create leaks.
  • Forgetting the insurer. A mezzanine or a crane with no approved drawings can void part of your cover.
  • Skipping the as-built drawings. At handback, the landlord asks what you changed. Good drawings protect your deposit.

Get a shortlist

During the site check we note the structure, the slab load, the clear height and any past mezzanines, so you can judge what fit-out the unit can take. Send your requirements and tell us if you need a mezzanine or a crane. We reply within 24 business hours. Tenants pay nothing.

Frequently asked questions

Does a mezzanine in a leased factory need a construction permit?

It depends on the size, the structure and where the factory sits. Some works in industrial parks are exempt from a permit but still need design review, landlord consent and a fire check. Ask the park management board and the local construction authority.

Do I need the landlord's consent for fit-out?

Yes, for anything that touches the structure, the roof, the slab, the fire systems or the outside of the building. Get consent in writing, with the drawings attached.

Which works are usually safe without a permit?

Light interior work such as movable partitions, painting, lighting and racking that does not change the structure or fire layout is usually low risk. Still tell the landlord and the park, and confirm with the authority if in doubt.

What is the risk of building a mezzanine without approval?

A stop order, fines, an order to remove the works and trouble with insurance and fire approval. The landlord may also treat it as a breach of the lease.