What a Standard Factory Needs Before You Build a Cleanroom in It
November 4, 2026
Yes, you can build a cleanroom inside a ready-built factory in Vietnam, and most tenants do it that way. The cleanroom is a fit-out inside a standard shell, so the question is not “does this unit have a cleanroom” but “can this building carry one”. Five parts of the base building decide the answer: height, floor, roof, power and fire approval.
Class decides how demanding the base building is
Cleanrooms are rated by particle count in the ISO 14644-1 classes. See the overview of cleanrooms on Wikipedia for the class table. A rough guide to what each level asks of the building:
| Class range | Typical use | What it asks of the base building |
|---|---|---|
| ISO 8 | Assembly, packaging, some medical device parts | Moderate. Many standard shells can host it |
| ISO 7 | Electronics, medical devices, optics | Good height, strong power, well-sealed envelope |
| ISO 5 and cleaner | Semiconductor, sterile and precision work | Special sites. Vibration, power quality and plant space matter a great deal |
Your cleanroom designer and your customer’s audit requirements set the class. Settle that first, then look for buildings.
The five base-building checks
1. Clear height
A cleanroom needs the room itself, a ceiling void for filters and ducts, and often an air handling plant on the roof or above the ceiling. Units with 8 to 10 m of clear height are the usual starting point. At 7 m it may work only for a low room with plant outside. Measure under the lowest beam, not at the ridge. Ask your designer for the total stack before you visit.
2. Floor
The floor needs to be level, dense and free of cracks that will open under load. Check:
- Flatness. Epoxy and vinyl systems show every dip.
- Load. Cleanroom equipment and wall systems add weight. See our guide on floor load capacity.
- Moisture. Slab moisture can make coatings fail. Ask whether the slab has a moisture barrier and look for stains at wall bases.
- Joints and drains. Floor drains inside clean areas are normally avoided. Check where the existing ones are.
3. Roof and envelope
A leak above a cleanroom is a quality problem and a safety problem. Visit after a rain if you can. Look for stains, rust at purlins, damaged sheets and gaps at wall-roof joints. Ask who repairs the roof during the lease and how fast. Heat gain through the roof also loads the air conditioning, so check roof insulation and skylights.
4. Power
Cleanroom air handling, chillers and filters run all day. In many cleanrooms the HVAC load rivals the machine load. Give the landlord your total connected load including HVAC, ask for the transformer size in kVA and check whether a new transformer or a second feed is possible. A cleanroom that needs a power upgrade can delay start-up by months. Our guide on reading transformer size and kVA shows how to check this.
5. Space for plant
Air handling units, chillers, cooling towers, pumps, exhaust fans and electrical rooms need space on the slab, on the roof or in the yard. Check:
- yard or roof area that can carry the plant
- a route for cranes or trucks to lift heavy equipment in
- noise and vibration limits toward neighbours
- drain points for condensate and chiller water
Fire safety and permits
A cleanroom divides the building into new rooms with new materials. Panels, doors, ceilings and plenum spaces change how smoke, sprinklers and detectors work. Before you build, ask:
- Does the approved fire design allow the new layout?
- Do sprinklers, detectors and exits need to change?
- Does your process add chemicals, gases or flammable materials?
- Which approvals do you need from the fire authority and the park management board?
A change of use or layout can trigger a new fire approval. See our guide to fire safety approval for what to ask to see. Confirm the path with a licensed adviser or the park management board before you order panels.
Fit-out, contractors and timing
The cleanroom is normally designed, built, tested and handed over by a specialist contractor. Typical steps:
- Fix the class, area and process layout.
- Choose a unit that passes the five checks above.
- Agree the works and landlord consent in the lease.
- Design, get approvals and order long-lead items such as air handlers.
- Build, balance the air, test and certify the room.
- Run a trial before you take customer audits.
Do not plan production on the day the lease starts. Allow time for design, approval, build and testing after handover. Ask for rent-free months for fit-out, as described in our guide on the rent-free period.
Looking for a factory now? Send my requirements
Medical, pharma and food: talk to your regulator early
Some products, such as medical devices, pharmaceuticals and some foods, carry their own manufacturing and registration rules. We do not advise on those. Ask your regulatory adviser what the product requires, then bring those requirements to the site visit so the building can be checked against them.
Questions for the landlord
- What is the clear height under the lowest beam?
- What is the floor load and flatness, and is there a moisture barrier?
- Has the roof leaked, and who repairs it?
- What is the transformer size, and can it be increased?
- Where can the plant go, and how does it get there?
- Will you consent in writing to partitions, ducts and roof penetrations?
- What must be removed at the end of the lease?
What the cleanroom does to your budget and your rent
A cleanroom adds three kinds of cost to the lease:
- Build cost. Panels, ceiling, filters, flooring, doors, pass boxes and air handling. Get quotes from cleanroom contractors for your class and area. Do not use a figure from a different class.
- Running cost. Air handling runs around the clock in most designs. The electricity bill is higher than for a normal plant of the same size, so ask your designer for the expected load in kW and add it to your power estimate. See the guide on electricity cost for factories.
- Exit cost. At the end of the lease the landlord may ask you to remove the cleanroom and repair the floor and roof. Settle this in writing before you build. Our guide on reinstatement at lease end shows what to include.
Common mistakes
- Choosing the unit before fixing the class. The class decides height, power and plant space.
- Counting only the room area. Gowning rooms, airlocks, material pass-through and plant rooms need floor area as well.
- Ignoring roof leaks. A small leak that is a nuisance in a warehouse can stop a cleanroom.
- Underestimating power. The HVAC load is added to the machines, and often forgotten.
- Starting fit-out before the lease allows it. Get landlord consent for ceiling hangers, roof openings and exhaust ducts first.
- Planning production on the day of handover. Build, balance and test time comes first.
Get a shortlist
Tell us the cleanroom class, the area and the total connected load, and we look for units that can carry it. We check height, floor, roof and power on site before a factory reaches your shortlist. Send your requirements and we reply within 24 business hours. Tenants pay nothing.
Frequently asked questions
Can I build a cleanroom inside a ready-built factory in Vietnam?
Yes, if the base building has enough clear height, a flat and strong floor, a dry roof, enough power and space for air handling plant. The cleanroom itself is built by the tenant as a fit-out.
Do you rent ready-made cleanrooms?
We search for ready-built factories. A cleanroom is normally a tenant fit-out inside a standard shell. If a unit already has one, we note its class and condition on site, but we do not certify it.
How much clear height does a cleanroom need?
More than a normal production floor. The room, the ceiling void and the air handling plant above it all take height, so units with about 8 to 10 m of clear height are the usual starting point. Your cleanroom designer sets the exact figure.
What is the biggest cost after the walls and ceiling?
Usually the air handling and cooling plant, and the electricity to run it. Cleanroom air conditioning often becomes one of the largest loads in the building, so check the transformer early.
Looking for a factory now?
Send your requirements. We reply within 24 business hours and shortlist up to 5 checked factories. No fee for tenants.
Send my requirements