From Brief to First Shipment: A Week-by-Week Timeline

November 21, 2026

For a leased, ready-built factory that fits your process, plan on about 6 to 8 months from a written brief to the first commercial shipment. The search and lease take 1 to 2 months. Registration, fit-out and power take most of the rest, and they overlap. A simple move can be faster. A project with a power upgrade, a machinery import or a large hiring plan is usually slower. These are planning ranges, not promises, and your own dates depend on your adviser, your suppliers and the landlord.

The timeline at a glance

Phase Typical weeks Starts after
1. Brief and shortlist 1 to 2 Day one
2. Site visits and choice 3 to 5 Shortlist
3. Lease terms and signing 5 to 9 Choice of site
4. Company and investment registration 6 to 14 Lease terms agreed in principle
5. Fit-out design, permits and power 9 to 20 Lease signed or handover agreed
6. Machine shipping and installation 10 to 22 Machine order, then handover
7. Hiring and training 12 to 24 Registration under way
8. Trial runs and first shipment 22 to 34 Machines running, staff trained

The weeks overlap on purpose. If you run the phases one after another, the total doubles.

Weeks 1 to 2: brief and shortlist

Write down the floor area, clear height, floor load, power in kVA, crane, dock count, move-in date and lease term you need. A clear brief lets a broker search the market in days. A vague brief produces ten visits and no decision. Our requirements brief guide shows what to include.

On our side, we reply within 24 business hours. A shortlist of up to 5 factories we have checked on site usually follows within a week.

Weeks 3 to 5: site visits and choice

Plan one visiting trip of two or three days and see all shortlisted factories in that window. Take the 12 checks from our ready-built factory checklist and score every site the same way. Ask each landlord for the fire approval documents, the land and building papers and a sample monthly invoice from a current tenant.

Two things from this phase decide the whole timeline: the power the unit really has, and the fire approval for your intended use. If either does not fit, you are signing up for an upgrade and a new approval, and both take months. A unit that fits today is often worth a slightly higher rent.

Weeks 5 to 9: lease terms and signing

Most of the time here is negotiation and translation, not paperwork. Expect two to four rounds on rent escalation, deposit, rent-free period, repair duties and exit rights. Agree the handover condition and date in writing. Use the lease clauses guide as a reading order, and ask a Vietnamese lawyer to review the final text.

Ask for a letter of intent or a lease commitment early. It holds the unit for you and can support your registration file while the full lease is finished.

Weeks 6 to 14: company and investment registration

A foreign manufacturer without a Vietnamese entity needs one before it can operate the factory, and the project usually needs investment registration at the same address. The legal processing times are short, but preparing the file, answering the authority’s questions and getting documents from your home country legalised take longer. Start this as soon as the site is chosen.

The order matters. In many cases the lease or a commitment is a required part of the investment registration file, and the registration then feeds the enterprise and tax steps. Read our guide to lease and investment registration and ask a licensed adviser to confirm the sequence for your business line.

Weeks 9 to 20: fit-out, permits and power

Fit-out is the phase with the most moving parts:

  • Layout drawings and a fit-out budget from at least two contractors.
  • Permits for any work that changes the structure, such as a mezzanine.
  • Fire prevention approval, updated if your process changes the use or the fire load.
  • Power: a new connection or transformer upgrade can take from weeks to several months.
  • Floors, partitions, lighting, compressed air, racking and offices.

If the unit needs only light fit-out, this phase can be 6 to 8 weeks. If it needs a power upgrade and a new fire approval, 4 to 5 months is realistic. A rent-free period during fit-out helps with cost, as the factory rent cost guide explains.

Weeks 10 to 22: machines

Order machines as soon as the lease is signed, since lead times for new equipment are often 8 to 16 weeks or more. Add sea freight, customs clearance and trucking to the park. If you plan to bring used equipment from another country, check the import rules early, as our guide to importing used machinery explains. Plan the installation date around the end of fit-out, not the start.

Looking for a factory now? Send my requirements

Weeks 12 to 24: hiring and training

Recruit supervisors and technicians first, then line workers in waves. Training usually starts on the first machines once they are installed. If you transfer experienced staff from another plant, include their visa and work permit time. See our hiring guide for how recruiting around a park works.

Weeks 22 to 34: trial runs and first shipment

Trial production, customer sample approval and quality audits come last. Many buyers require a sample approval before the first order, so allow time for at least one failed sample and a second round. First shipment follows once a stable batch passes your own inspection.

What shortens the timeline

  1. A complete brief in week one. Everything else starts from it.
  2. Power and fire checked before the lease. These two cause the longest surprises.
  3. Parallel work. Start registration, machine orders and recruiting before the lease is finished.
  4. One decision maker on site. Most delays are waiting for approval from headquarters.
  5. A handover date in the lease. Without it, fit-out cannot be scheduled.

Risks that add weeks

Most overruns come from a short list of causes. Watch these from week one:

Risk Typical effect How to reduce it
Transformer too small Months of waiting for an upgrade Compare your load with the unit’s kVA before the lease
Fire approval does not cover your use An updated approval before operating Ask to see the approval and the use it covers
Documents from home country not ready Registration waits Start notarising and legalising papers in week one
Machine fails a customs check Re-export or replacement Check age and standards before shipping
Landlord late on handover Fit-out and install slip together Put a dated handover and a remedy in the lease
Customer sample rejected Extra trial round Book the first sample early and plan a second

Add a buffer of two to four weeks for the items you do not control. A schedule with no buffer is a wish.

A week-one checklist

Before the search starts, collect these in one folder so nothing waits for a headquarters reply:

  1. The requirements brief with area, height, floor load, kVA, crane, docks, move-in date and term.
  2. The machine list with weights, dimensions, power and age.
  3. The name and business line of the entity that will lease, or a note that it does not exist yet.
  4. The decision maker and a backup who can sign.
  5. A budget with deposit, advance rent, fit-out and a contingency.
  6. The first customer deadline, so the whole plan can be counted back from it.

Once these are in place, the schedule becomes a simple counting exercise. Without them, each step starts late and the plan moves.

A note on the first shipment

The first shipment is not the end of the set-up. Expect the first months of output to run below planned capacity while crews learn the product, suppliers settle and quality records build up. Tell your customer the ramp-up curve at the start, and avoid committing full volume on day one. A realistic promise kept is worth more than an early date missed.

What to do next

Send us your area, power, height and move-in date and we will start the search. Send your requirements and we reply within 24 business hours. There is no fee for tenants.

Frequently asked questions

What is the fastest way to start production in Vietnam?

Lease a ready-built factory whose power, floor, height and fire approval already fit your process, and start company registration and machine orders while the lease is being negotiated. Steps that run in parallel save more time than any single step done faster.

Which step causes the most delay?

Power and approvals. A transformer upgrade, an updated fire safety approval or a late investment registration can each hold up production by months. Check them before you sign the lease, not after.

Do I need a Vietnamese company before I sign the lease?

Often the lease or a lease commitment is part of the investment registration file, so the order of steps matters. Ask a licensed adviser to confirm the order for your case before you sign.

How soon can I get a factory shortlist?

We reply within 24 business hours, and a shortlist of up to 5 checked factories usually follows within a week, depending on how specific your requirements are.