Guides / Setup
What Should a Machining or Fabrication Shop Check in a Rented Factory?
November 21, 2026
A machine shop or fabrication plant needs a stronger building than most other trades. Check four things before anything else: the floor load against your heaviest machine, the crane beams or lifting plan, the three-phase power available, and where coolant, oil and metal waste will go. A unit that fails on any one of these costs far more to fix than a few dollars of rent per m² can save.
This guide covers CNC machining, sheet metal, welding and light to medium fabrication in southern Vietnam. Heavy forging and foundry work are different and need special sites.
The four core checks
| Check | Why it matters for metal | What to ask |
|---|---|---|
| Floor load | Machines, presses, racking and forklifts | Slab rating in tons per m², thickness, condition, local foundation options |
| Crane | Moving parts, tooling and machines | Crane beams, span, rated capacity, runway length |
| Power | Spindles, motors, welders and compressors | Transformer kVA, phase balance, room to upgrade |
| Waste | Coolant, oil, chips and sludge | Where waste is stored, who collects, park rules |
Floor load and foundations
Metal plants are heavy. A 5-axis machining centre can weigh many tons on a small footprint. A press adds shock load. Heavy racking with bar stock adds point loads.
Collect the weight, footprint and any dynamic load for each large machine from the supplier’s documents. Then ask the owner for the slab rating and thickness. Many ready-built units list a figure in tons per m², but a point load under a machine foot is a different calculation. For precision machines, the question is not only strength but also vibration and levelling.
Some machines need their own foundation block, cut into the slab. Ask if the lease allows it, who approves the work and what condition you must hand back. See floor load capacity for how to read the numbers, and reinstatement at end of lease for the handback side.
Crane and lifting
If you move parts or machines above what two people can lift, you need a plan. The options:
- An existing overhead crane. Check the span, the rated capacity, the hook height and whether it is in service and inspected.
- Crane beams without a crane. The structure is ready and you buy the crane. Check the beam rating.
- No crane and no beams. You use forklifts and gantries. This works for light parts only.
Retrofitting a crane on a building not designed for it is expensive or impossible. If you plan to grow into a crane, ask whether the columns and roof can take it. Our guide to factories with an overhead crane goes through the checks, and the clear height guide explains why hook height matters.
Power: three-phase and clean
Machining runs motors, spindles and servo drives for long hours. Welding, plasma cutting and compressors add peaks. Compare your total connected load with the transformer, then apply a realistic demand factor with your engineer. Ask:
- Is the transformer dedicated to this unit?
- What is the voltage and how stable is it?
- How long does an upgrade take, and who pays?
Precision CNC machines are sensitive to dips and spikes. Ask the park about outage history and plan for stabilisers where needed. Read power supply in kVA for the basics.
Coolant, oil and metal waste
Machine shops create three kinds of waste that need planning:
- Chips and swarf. Collected by scrap buyers. Needs a covered bin area.
- Coolant and cutting oil. Used coolant and waste oil are generally treated as hazardous waste. They need sealed containers, a bunded store and a licensed collector.
- Sludge and filters. From coolant filters, washing and parts cleaners.
Ask the park management how hazardous waste is collected and whether it has approved contractors. Check that the unit has a place for a bunded store near an access road, not in the middle of the hall. If you wash parts or run plating or anodising, the wastewater question becomes much larger. See the environmental permit and wastewater fees.
Noise, vibration and neighbours
Fabrication with grinding, hammering and pressing makes noise. Parks usually have limits at the boundary of each unit. Ask the management board for the limits, and walk the building when neighbours are running. A precision shop next to a press shop can have a vibration problem on both sides.
Looking for a factory now? Send my requirements
Floor, height and layout
Straight material flow saves money: bar stock in, cutting, machining, deburring, cleaning, inspection, packing and out. A clear-span hall of 9 to 10 m height with a 15 to 20 m wide crane bay suits many shops. Smaller shops may do well in a 7 to 8 m building with no crane, if parts are light.
Plan space for:
- A temperature-controlled room for measuring and inspection
- A tool room and a store for fixtures
- A clean area for finished parts and packing
- Offices and a break area, and parking
Lead time for fit-out
Moving heavy machines in takes planning. Check that the access route, the doors and the dock height allow your largest machine to enter. Allow time for foundations, compressed air, coolant systems and electrical connections. A site visit with your machine supplier’s installer is worth the day.
Who this does not suit
Large forging, foundry, heat treatment and heavy paint lines have stricter rules and often need a dedicated plot, not a ready-built unit. If your plan includes any of them, say so in your first message.
Measurement, cleanliness and temperature
Precision parts need a stable environment. If you machine to tight tolerances, plan a measurement room with stable temperature and no vibration from neighbouring machines. The building shell decides how hard that is. An insulated roof and sealed walls help. A slab near heavy presses or forklift routes does not.
Also plan a separate clean area for finished parts and packing. Oil and chips travel on shoes and trolleys, so a clear boundary between machine floor and packing area saves rework.
Compressed air and utilities
CNC machines run on compressed air, and coolant systems need electrical connections and drainage. Check whether the building has a compressor room or space for one, and if the floor can take drainage channels. Cable trays, lighting levels and ventilation for welding fumes are also fit-out items. Welding and grinding need extraction, so ask about roof openings for ducts.
Questions to ask on the first visit
- What is the slab rating under the area where the heaviest machine will go?
- Is the crane in service, and when was it last inspected?
- Can I see the transformer plate and the last six months of power bills?
- Where is the hazardous waste store and who collects?
- What noise and vibration limits does the park enforce?
Spare parts, service and people
Machine shops depend on skilled technicians and fast service from machine suppliers. Look at where the nearby supplier base sits: tooling, coolant, gauges, heat treatment, anodising and surface finishing. A park in the Binh Duong area, now part of Ho Chi Minh City, or in Dong Nai usually has these services within a short drive. A more remote site may save rent but cost more in downtime. Also check where machinists live and how they reach the park.
Get a shortlist
Tell us your heaviest machine, crane need, kVA and area, and we will check units on site against them. Send your requirements and we reply within 24 business hours with up to 5 factories we have checked.
Frequently asked questions
What floor load does a machine shop need?
It depends on the machines. Light CNC lathes and mills may sit on a standard industrial slab, while large machining centres, presses and heavy fabrication need a stronger slab or local foundations. Get the weight and footprint of each machine and ask the owner for the slab rating.
Do I need an overhead crane for machining?
For parts or machines above a few hundred kilograms, usually yes, or at least a forklift route and a plan for lifting. For fabrication of large frames, a crane is a core tool. Check whether crane beams already exist and their rated capacity.
Is coolant and oil waste a problem in a leased unit?
It can be. Used coolant, oil and metal sludge are usually handled as hazardous waste and need proper storage and a licensed collector. Ask the park how it works, and plan a bunded area in the unit.
How loud can a machine shop be in an industrial park?
Parks have rules on noise and vibration at the boundary. Fabrication with presses and grinders is louder than CNC machining. Ask the park management board for its limits and check neighbouring tenants.
Looking for a factory now?
Send your requirements. We reply within 24 business hours and shortlist up to 5 checked factories. No fee for tenants.
Send my requirements