What Do Water and Wastewater Cost in a Vietnam Industrial Park?

November 21, 2026

Water and wastewater are billed per m³, on top of rent and the management fee. Water is charged at the park’s rate for the volume you use. Wastewater is charged separately, often as a share of the water you buy or from a discharge meter, and it may carry a minimum monthly charge. For offices and light assembly the bill is small. For plating, dyeing, food processing and washing lines it can be a major cost, and the discharge limits can decide whether the park accepts your process at all.

What appears on the invoice

Line How it is charged What to ask
Clean water Per m³ at the park or supplier rate Is the rate fixed or does it follow the supplier’s tariff?
Wastewater treatment Per m³, often a share of water volume, or metered discharge What share is used and who reads the meter?
Minimum charge A base volume or amount per month Does it apply during the rent-free months?
Environmental protection fee A state fee on industrial wastewater, where it applies Is it passed through to you, and how is it calculated?
Meter or connection fee One-off Who pays for installing and checking meters?
VAT On top of the above Which rate applies to each line?

Clean water supplied through the network and wastewater treatment can carry different tax treatment, so ask your adviser how each line is invoiced.

How wastewater volume is set

Most parks do not measure every tenant’s discharge separately. The common methods are:

  1. A share of water bought. If the contract says wastewater is billed at 80% of water supplied, then 1,000 m³ of water in a month gives 1,000 m³ of water charge plus 800 m³ of wastewater charge. This is simple, but it overcharges plants that lose a lot of water through evaporation, cooling towers or product content.
  2. A discharge meter. A flow meter on your outlet. It is more accurate and fair for water-heavy processes, but the meter costs money and needs calibration.
  3. An agreed fixed volume. Used for small tenants, with a true-up if usage changes.

If your process loses a lot of water, ask for a meter or a lower share. The saving over a three year lease can pay for the meter many times.

Discharge limits

The park treats all tenant wastewater in a central plant. To protect it, the park sets inlet limits: the maximum concentration of pollutants a tenant can send to the plant. These follow the national industrial wastewater standard or something stricter, set by the park. Typical limits cover acidity, suspended solids, oil, heavy metals and organic load.

Three situations matter:

  • Domestic type wastewater from toilets, canteens and washing. Usually acceptable with simple traps, such as grease traps in canteens.
  • Process wastewater from washing, cooling, painting, plating, dyeing or food. May need pretreatment on site to meet the inlet limits.
  • Hazardous liquids, such as spent solvents, oils and coolants. These are not discharged to the sewer at all. They are collected as hazardous waste by a licensed contractor.

Ask the park for its inlet limits in writing and compare them with your process data. If you do not know your wastewater profile yet, ask your equipment supplier or a consultant for an estimate before you lease. A plating line that cannot meet the limits leaves you with either a pretreatment plant or a different site.

The cost of pretreatment

Pretreatment is a fit-out cost, not a monthly fee, but it changes the whole budget. A basic system for oily water or washing water needs space, a tank, equipment and a licensed operator. Check these points before you sign:

  • Is there space on the plot for tanks and equipment, and does the lease allow building them?
  • Who designs and operates the system, and does it need a permit?
  • What does the park test at the inlet, how often and how does it bill for sampling?
  • What if your discharge fails a test: a surcharge, a warning period or a cut-off?

Our guide to environmental permits for a factory shows when the paperwork starts, and the fit-out cost guide covers how to include pretreatment in your budget.

Water supply details to confirm

  • Source and pressure. Network water, a park supply line or boreholes. Pressure matters for cooling, washing and fire protection.
  • Reliability. Ask tenants about shortages in the dry season.
  • Water tank and pump. Whether the unit has a ground tank and a pump, or whether you must add one.
  • Fire water. Fire protection needs its own supply and tank. Our fire safety approval guide covers what to ask to see.

Looking for a factory now? Send my requirements

A quick estimate method

  1. List the water uses: staff (toilets, canteen), process, cooling top-up, cleaning.
  2. Estimate volume per day for each, and multiply by working days.
  3. Apply the park’s wastewater share, or your own discharge estimate if a meter is used.
  4. Multiply each volume by the park’s rates. Add the minimum charge if it is higher.
  5. Add pretreatment operating costs, if any.

For an office and assembly plant with a few hundred staff, most water goes to toilets and the canteen, and the bill is modest. For a food or dyeing plant, process water dominates, and the bill needs a proper calculation with real rates from the park.

Questions to ask the park

  • What are the water and wastewater rates per m³, and are they fixed for my lease term?
  • What share of water is billed as wastewater, or is there a discharge meter?
  • Is there a minimum monthly charge, and when does it start?
  • What are the inlet limits for my process, and how often are they tested?
  • What are the consequences of a failed test?
  • Does the park take process wastewater from my industry at all? See also our note on whether your business line fits the park.

What it looks like by industry

The table shows the pattern in general terms. Your process and your volumes decide the real answer.

Process Water use Wastewater issue Typical action
Assembly, packaging, warehouse Low, mostly toilets and canteen Domestic type Standard connection and a grease trap for a canteen
Machining and metalworking Low to medium Coolant and oily water Coolant recycling, oil separation and licensed waste collection
Plastics injection Medium, cooling water loop Usually little process wastewater Closed-loop chillers and cooling towers
Food processing High Organic load, fats, solids Pretreatment, screening, fat traps
Textile dyeing and washing High Colour, chemicals, high load Park must accept it; strong pretreatment
Plating and surface finishing Medium Heavy metals, acids Often limited to specific parks; strict controls

Do not sign a lease for a process in the last two rows without written acceptance from the park management board that it takes your wastewater type.

Rainwater and drainage

Rain falls heavily in the south during the rainy season, and runoff from yards and roofs is separate from wastewater. Check that the unit has its own storm drain connection, that the yard slopes away from the building and that process areas are covered or bunded, so rain does not carry spills into the storm drain. Spills into the storm system are treated more seriously than discharges into the sewer.

Get a shortlist

If your process uses a lot of water or produces process wastewater, say so in your request, since it removes some parks from the list at once. Send your requirements and we reply within 24 business hours. We check water, drainage and the connection to the park plant on site. Tenants pay no fee.

Frequently asked questions

How is the wastewater fee calculated in an industrial park?

Parks commonly bill wastewater per m³, either as a share of the water you buy or from a discharge meter. The share and the rate are set by the park, so ask for them in writing.

Is there a minimum monthly water or wastewater charge?

Some parks charge a minimum, so a quiet month still carries a base bill. Ask for the minimum in m³ or in dong, and whether it applies from handover.

What happens if my wastewater exceeds the park limits?

Parks usually apply a surcharge, require pretreatment or can limit the connection until the discharge meets the limits. Agree the limits and the consequences before you sign.

Do I need my own wastewater treatment?

It depends on the process. Offices and light assembly usually need none beyond the park connection. Plating, dyeing, food, washing and painting processes often need pretreatment on site to meet the park's inlet limits.