Which Utilities Come With a Rented Factory, and Which Do You Build?
November 15, 2026
Most ready-built factories in Vietnam come with the basics: a power connection, a water supply, drainage and basic lighting. Everything else that makes your process run, such as compressed air, process gases, cooling water and cable routes, is usually yours to design and pay for. Knowing which is which before you sign lets you price the fit-out correctly and avoid a unit that cannot support your process.
What usually exists and what does not
| Utility | Usually in a ready-built unit | Usually tenant fit-out | Ask the landlord |
|---|---|---|---|
| Power | Transformer, main board | Distribution boards, machine feeders, busbars | Size in kVA, dedicated or shared |
| Water | Mains supply and meter | Internal pipes, tanks, treatment | Pressure, minimum charges |
| Wastewater | Connection to park system | Pre-treatment if your process needs it | Discharge limits |
| Compressed air | Rarely | Compressor, dryer, receiver, pipes | Roof and floor loads, space for a room |
| Process gas | Rarely | Tanks, manifolds, safety systems | Storage rules, fire approval |
| Cooling water | Rarely | Chillers, towers, pumps | Yard space, roof load |
| Cable trays and conduit | Basic lighting only | Power, data and control trays | Fixing points on the roof steel |
| Ventilation | Roof vents, maybe fans | Extraction, cooling, fresh air | What the roof can carry |
For power, read our guide on transformer size and kVA first. The rest of this article covers the items people forget.
Compressed air
Compressed air is the utility most often missing from the budget. A tenant with a few pneumatic tools needs a small compressor. A plant with many presses, injection machines or packaging lines needs a proper system.
Plan the system from the machine list. Add the air demand of each machine from its manual, then ask a compressor supplier to size the unit and the receiver. Do not size it from the building.
Pick the room early. The compressor room needs:
- ventilation that removes heat, and a clean, shaded air intake
- a floor that carries the weight and takes vibration
- a short, direct route for the main pipe
- room to reach filters and belts for service
Think about air quality. Food, electronics and painting often need dry, oil-free air. Quality is described by the ISO 8573-1 classes. Say which class your process needs and ask the supplier for dryers and filters to match.
Check the roof and walls. Heavy pipes, tanks and cooling units hang on the roof steel or sit on the slab. Ask the owner for the permitted load before you fix anything.
Process gases
Nitrogen, argon, oxygen, LPG and others come either in cylinders, in tanks or from on-site generators.
- Cylinders need a cage, a safe route and a fire plan.
- Tanks need a pad, a refill route for trucks and approval that matches the stored volume.
- Generators (for example nitrogen) need power, compressed air and space.
Piped gas is not available in every park. If your process needs a continuous supply, ask the park management whether a network exists before you rely on it. Whatever the source, tell the fire authority and the landlord what you plan to store. Storing gas is a change of use that can affect the fire approval. Our guide on fire safety approval shows what to ask to see.
Water, cooling and drainage
Check water in three places:
- Supply pressure at the point of use. A meter reading on the street does not tell you what arrives in the building.
- Storage. If the park supply is interrupted, a rooftop or ground tank keeps washing and cooling running.
- Drain points. Floor drains, trenches and sumps take wash water and spills. Check that they slope to the right place and connect to the park system.
Plastic injection, plating and food plants add cooling towers or chillers. These need yard or roof space, power and a way to treat or recirculate the water. Ask what the park allows. For the money side of water and wastewater, see the guide on wastewater fees in industrial parks.
Cable trays, grounding and data
Cabling is a utility too. Ready-built units often have only lighting circuits at roof level. A tenant has to add:
- Cable trays for power, control and data, separated to avoid interference
- Earthing and grounding that meets the needs of your machines and any ESD flooring
- Lightning protection if not yet in place
- Network and server room cabling, with space and power for the room
Ask where cable trays can be fixed and whether the roof purlins take the extra load. In multi-tenant buildings, ask where your trays can run without crossing a neighbour’s area.
Looking for a factory now? Send my requirements
What to do on the visit
Bring your machine list and walk the unit with these questions:
- Where does each machine sit, and can power, air and water reach it without crossing aisles?
- Where would the compressor, chiller and tank go?
- What is the roof and slab load allowed for new equipment?
- Is the yard big enough for a gas tank, a chiller and a truck turn?
- Which utilities has the landlord already put in, and in what condition?
Write the answers on the same sheet for every unit. Then price the fit-out for each unit and compare the totals, not just the rent.
Agree the exit terms now
At the end of the lease, pipes, tanks and cables can become a dispute. Decide before you sign what the tenant removes and what stays, and who repairs holes in the roof and floor. Take photos of the starting condition at handover. A short handover report makes this easy to prove later.
How to budget utilities without guessing
Utilities are a large part of fit-out, and the cost depends on the process. Do not use a figure from another plant. Build the budget in four steps:
- List every utility each machine needs from its manual: power, air, water, cooling, gas, exhaust.
- Sketch the pipe and cable routes on a copy of the floor plan. Longer runs cost more and lose more pressure.
- Ask two or three contractors for written quotes for the same scope, split by utility.
- Add the lease items: the landlord’s consent for roof penetrations, any works done by the park and the cost of restoring the unit at the end.
Keep the quotes next to the rent comparison. A unit with lower rent but no yard space for a chiller, or no safe place for a compressor room, can cost more over the lease term than a dearer unit that fits. The fit-out guide shows the main line items.
Common problems found on site
- Pipes fixed to roof sheets, not to the steel. Sheets leak and bend under the load.
- Compressor intake in a hot corner, which wastes energy and shortens the life of the machine.
- Undersized main pipe, causing a pressure drop at the far machines.
- Drains that slope the wrong way, leaving water standing near machines.
- Cable trays that cross exits, which creates a fire and access problem.
- No plan for expansion, so adding a second compressor means breaking into the wall.
Most of these show up during the first walk if you bring the machine list and ask where each item goes.
Get a shortlist
If you send us your machine list and the utilities your process needs, we check on site which units can support them and which need work before a factory reaches your shortlist. Send your requirements and we reply within 24 business hours. Tenants pay nothing.
Frequently asked questions
Does a ready-built factory in Vietnam include compressed air?
Usually not. Most ready-built units come with power, water, drainage and lighting. Compressed air, process gases, chilled water and dedicated cabling are normally part of the tenant fit-out.
Where should the compressor room go?
Place it where noise and heat do not reach the line, with an air intake that is shaded and clean, and with a short pipe run to the main users. Check that the slab and the ventilation can take the equipment.
Is piped gas available in industrial parks?
Not in every park. Many plants use LPG tanks or other supplies. Ask the park whether a gas network exists, and check the storage rules and fire approval for tanks.
Who pays for utility changes when I leave?
It depends on the lease. Agree before you sign whether you remove pipes, tanks and cabling, or leave them. Photograph the starting condition on handover day.