Does the Factory Flood? How to Check Before the Rainy Season

November 20, 2026

Check four things to judge flood risk: how high the floor sits above the road and the surrounding ground, how the park and the site drain, what the water marks and past events show, and what happens to access when the roads flood. Do this in the rainy season if you can. A dry-season visit hides the problem.

Most industrial parks in the south are designed with drainage and raised platforms, and many never flood. Some low-lying sites, and some older or poorly drained areas, do. The point is to find out before you pay a deposit.

What causes flooding here

Southern Vietnam has a rainy season, roughly from May to November. Three things can bring water into a site:

  1. Heavy rain that overloads drains faster than they empty.
  2. High tides that push water up rivers and canals and stop drains from discharging. This is a known issue in low parts of Ho Chi Minh City and along rivers and canals.
  3. Overflow from rivers or reservoirs after long rain or releases upstream.

Poor local drainage, blocked canals and fill on nearby land add to the risk. Each park and each site differs, so check the specific address.

Check the floor level

Floor level is the single most useful number.

  • Floor above the road. A raised dock and floor sit above street water. Measure the step from the road or apron to the floor.
  • Floor above surrounding ground. If the factory sits in a dip, water will flow toward it.
  • Dock and door thresholds. Roller doors at ground level let water in first.
  • Pits and trenches. Cable trenches, floor drains and pits can fill from below.

Ask the landlord for the design flood level and the finished floor level if they are known. Photograph the dock and the entry with a tape measure.

Look for signs of past water

Walk the site and look for:

  • tide or water marks on walls, columns, fences and machine bases
  • paint peeling or mould on the lower walls
  • stains and silt in corners, trenches and the dock
  • new patches of concrete, plaster or paint at low level
  • rust at the base of columns and racking

A fresh coat of paint on the bottom metre of a wall can be a sign too. Ask why it was done.

Drainage on and around the site

  • Where does rain from the roof go? Look at gutters and downpipes and where they discharge.
  • Are there storm drains on the site and the park roads, and are they clear?
  • Where does the park drain to: a canal, a river, a pond? What stops water coming back in at high tide?
  • Does the park have a pump station or retention pond?
  • Are there blocked, silted or full drains after rain?

Our roof guide covers the roof side of rainwater.

Access during floods

A dry factory with flooded roads still stops work. Check:

  • the roads that workers and trucks use to reach the park
  • low points, underpasses or bridges on the route
  • the main road into the park and how often water covers it
  • whether workers live nearby, or travel from areas that flood

Ask the park management how many days work stopped in the last rainy season. Ask neighbouring tenants too, and compare the answers.

Ask the right people

Source What to ask
Landlord Has the unit flooded? When and how deep? What was done?
Park management Any flooding in the park? Drainage upgrades?
Neighbouring tenants Did production stop? Was stock damaged?
Local drivers Which roads flood and for how long?
Your insurer Is flood covered, and are there exclusions for this location?

Get answers in writing where you can.

What to put in the lease

If risk is not zero, protect yourself:

  • The landlord states the unit has not flooded, or lists past events.
  • A repair duty for drainage and floor defects.
  • A right to suspend rent or end the lease if flooding or lost access repeats.
  • Permission to fit flood barriers, raised racking, sump pumps or non-return valves.
  • A clear split of insurance between tenant and landlord. Read our tenant insurance guide.

Looking for a factory now? Send my requirements

Reduce the impact

If you take a unit with some risk, there are cheap ways to cut damage:

  1. Keep stock and electrical gear off the floor, on racks or plinths.
  2. Place electrical panels, sockets and control cabinets above expected water levels.
  3. Keep flood barriers or sandbags and a pump.
  4. Write a simple flood plan: who moves stock, who cuts power, who calls whom.
  5. Back up data and key records off site.

Put it in your checklist

Flood risk belongs with the other site checks. Use the ready-built factory checklist to keep all of them in one place, and the infrastructure check for industrial parks for the park-level view.

A rainy-season visit plan

If you can only visit once, choose a day after heavy rain, ideally in the later months of the season. Then:

  1. Arrive early and check the roads to the park. Note any standing water.
  2. Walk the park perimeter and the drains. Look at water levels and the flow.
  3. Visit the unit and look at the dock, the trenches and the low parts of the floor.
  4. Talk to a security guard or a neighbour who has been there a while.
  5. Take dated photos of everything that looks wet or stained.

If your schedule does not allow this, ask for dated photos from the last rainy season and compare with your own on a dry day. A landlord with nothing to hide will usually share them.

Weigh flood risk against other factors

A site with a modest flood risk is not always out. It may carry a lower rent or a better location. The question is whether the risk fits your goods. Electronics, paper, textiles and food suffer badly from water, while some metal parts handle a short event with little damage. Match the unit to your product, and price in the insurance, the barriers and the lost days.

If your goods are high in value and sensitive to water, choose a unit at a higher level in a park with a good drainage record, even if the rent is higher.

Record what you find

Keep a short flood file for each unit on your list: the floor level against the road, photos of the drains and the dock, notes from the park management and neighbours, and what the landlord said. Write the date and the weather on each photo. If you later sign, this file is your baseline. If a dispute comes up over damage or a lost month of production, you can show what was known at the time.

Add a line to your lease file for the park’s own plans. Some parks upgrade drains, raise internal roads or build pump stations. Ask what is planned and when, and whether the landlord will tell you about works that may affect access.

Get a shortlist

We ask about flooding at every site, look for water marks and note the floor level against the road before a unit goes on your shortlist. Send your requirements and we reply within 24 business hours. Tenants pay nothing.

Frequently asked questions

When is the rainy season in southern Vietnam?

Roughly from May to November, with the heaviest rain commonly in the later months. Tides and heavy storms can raise water levels in low areas near rivers and in parts of Ho Chi Minh City.

How can I find out if a factory has flooded before?

Ask the landlord, the park management and neighbouring tenants. Look for water marks on walls and columns, stained dock areas and patched floors. Photos taken in the last rainy season are the best evidence.

Does flood damage count as an insured risk?

It depends on the policy. Some cover flood only as an add-on. Ask your insurer in writing and compare with the landlord's cover. Our tenant insurance guide lists the questions.

Can I leave if the factory floods?

Only if the lease allows it. Ask for a clause that covers repeated flooding or loss of access, with a rent suspension or a right to end the lease.