How Big a Factory Should You Rent? Size It From Your Process

November 21, 2026

Size a factory from your process, not from a headcount rule. List every step from raw material to shipped goods, give each step the floor it needs, add storage, offices and worker areas, then add a margin for growth. The result is a number in square metres that you can test against real units. Most tenants who rent too small or too large skipped this step and picked a unit because a listing looked right.

This guide gives a method you can finish in an afternoon. The numbers in the examples are made up to show the arithmetic. Use your own.

Step 1: draw the flow

Write the steps of your process in order. For a metal parts plant it might be: incoming material, cutting, machining, deburring, cleaning, inspection, packing, dispatch. For electronics: incoming goods, SMT line, assembly, test, packing. Draw a rough block layout, one box per step, with arrows for material flow.

A straight flow often needs a long, narrow floor. A U-shaped flow needs a more square floor. The shape of the building matters as much as the area. Column spacing can break a layout, so check it using the site checklist.

Step 2: give each box an area

For each step, add up:

  • The machines or workstations, including the space an operator needs.
  • Space for material in and out.
  • Maintenance access. A press or CNC machine needs room on the sides to open covers and change tooling.
  • Utilities: compressors, chillers, dust collectors and panels. See utilities in a factory.

Use supplier drawings for machine footprints. Ask for the working envelope, not just the base size.

Step 3: storage

Storage is the area that people underestimate most. Plan for:

  • Raw material and parts. How many days or weeks of stock do you hold? Import lead times from China or elsewhere can mean weeks or months of stock.
  • Work in progress. Buffers between steps.
  • Finished goods. Until the next truck or container.
  • Packaging. Cartons and pallets take more room than most plans expect.

If you use racking, clear height changes the answer: tall racking can cut floor area by a large part. Read our clear height guide and check the floor load.

Step 4: support areas

Area What to count
Offices Desks, meeting room, quality lab, server room. See office space in a factory
Worker facilities Toilets, changing rooms, canteen, rest area, parking
Receiving and dispatch Dock area, staging lanes, container turning
Waste and scrap Bins, scrap bay, chemical store if needed
Maintenance Spare parts, workshop, tool crib

Check what the unit already includes. Some units have offices attached. Others require you to build them inside the hall, and the area comes out of production space. Read our guide to worker facilities, canteens and parking.

Step 5: walkways and safety

Factories need aisles, escape routes and fire access. Do not fill every metre with machines. Fire rules affect aisle width and storage layout, and a crowded layout can also fail a customer audit. Ask a consultant to check the layout. Our fire approval guide lists the points to cover.

Step 6: add growth

Decide how much extra space you will want in the first 3 years. Common approaches:

  1. Rent exact size and take a right of first offer on an adjoining unit. The landlord must tell you if the neighbouring space becomes free.
  2. Rent a bigger unit and sublet or leave part empty for the first year. This costs rent for unused floor.
  3. Plan a second unit in the same park, so staff and logistics stay together.

Ask the landlord what is possible. If rapid growth is likely, a larger or built-to-suit project can be a better fit.

A worked example

This example is made up to show the method.

Item Area (m²)
Machining and assembly lines 900
Raw material store 200
Finished goods store 250
Inspection and quality lab 80
Packing and dispatch 150
Support (maintenance, utilities, waste) 120
Aisles and escape routes 300
Subtotal, production hall 2,000
Offices and worker facilities 300
Growth margin of about 15% on the hall 300
Total 2,600

If you rent at the typical range of about US$4 to US$7 per m² per month seen on public listings, 2,600 m² would cost roughly US$10,400 to US$18,200 a month in rent before VAT and fees. A 2,000 m² unit would be US$8,000 to US$14,000. The difference between sizes is real money each month, so test whether you need the growth margin on day one. See our cost guide for the other items on top of rent.

Looking for a factory now? Send my requirements

Match the size to the market

Unit sizes vary by park. Many ready-built units fall between 500 and 10,000 m². If you need under about 1,500 m², read our small factory guide. If you need 10,000 m² or more, read the large factory guide. If your plan needs several floors, see multi-storey factories.

Write the size into your brief

When you ask landlords or brokers for units, give a range, not a single number: for example, 2,200 to 2,800 m² of production hall, plus 200 to 300 m² of offices. A single number can exclude good units. Also state clear height, floor load, power and crane. Use the requirements template.

Common sizing mistakes

  • Taking the listing area as production area.
  • Forgetting the area for waste, utilities and quality control.
  • Counting a mezzanine as full floor when it needs a permit. See mezzanine permits.
  • Sizing for peak volume that may not arrive for years.
  • Choosing a unit whose column grid does not fit your lines.

Test the number against three cases

Before you search, run your size through three cases.

  1. Low case. Demand is 30% below plan for a year. Can you still afford the rent? If not, the unit is too big or the lease too long.
  2. Plan case. Everything works as planned. Does the layout still flow without crowding?
  3. High case. Orders grow faster than planned. Where does the next line go: an adjoining unit, a second building or a mezzanine?

If the answers are uncomfortable, adjust the size or negotiate flexibility into the lease, such as a renewal option or an early termination right. Our early termination guide explains the usual terms.

Who to ask for help

Your equipment supplier can give footprints and utility needs. A layout consultant can test the flow. Landlords often have drawings of the unit as built, which let you place machines on paper before a visit. Ask for them.

Check the size against the people

Headcount is a check, not a method. Once you have the area, divide it by the planned number of workers per shift and compare with the layout. A very low area per person can mean you have oversized storage. A very high one can mean a crowded plan. Use this only as a sanity check and ask your layout consultant for the numbers that suit your process. Also confirm that toilets, canteen and parking fit the headcount, since the park and the fire rules can limit the number of people per building.

Get a shortlist

Send your area range, height, power and crane needs through the request form. We check the usable area on site and send a shortlist of up to 5 factories. We reply within 24 business hours. Tenants pay nothing.

Frequently asked questions

How do I estimate the factory size I need?

Add the area of each process step, material and finished goods storage, offices and worker facilities, then add space for walkways and growth. Start from your line layout, not from a rule of thumb per worker.

Should I rent more space than I need today?

Only if the extra space is cheaper than moving later. Ask for an option on an adjoining unit or the right to take more space in the same park, instead of paying for empty floor from day one.

Is the listed area the area I can use?

Not always. Listings may include canopies, office floors and mezzanines. Ask for the production floor area on its own and measure the clear floor between columns.

What happens if I outgrow the unit?

You can add a second unit, move or build. Agree early whether the landlord can offer more space, and check your lease for early exit and renewal terms.