Guides / Finding
What Happens If You Lease a Factory That Has No Valid Fire Approval?
November 21, 2026
A factory without valid fire approval for your use can delay your start-up, bring penalties and, in a bad case, force you to stop operating, while your rent runs. The risk is not only legal. Insurers, customers’ auditors and lenders ask for the papers. The safe approach is to check the approval and acceptance before you sign, compare the approved use with your process, and put a clear remedy in the lease for the case where the papers fail.
This guide describes the risks and the protections. It is general information, not legal advice. Fire rules changed recently, so ask the fire authority or a licensed consultant to confirm what applies to your building.
What the rules look like now
A new Law on Fire Prevention, Fighting, Rescue and Salvage (No. 55/2024/QH15) took effect on 1 July 2025, with Decree 105/2025/ND-CP guiding it. The decree replaced Decree 136/2020/ND-CP. It sets which works need fire design appraisal and lists the facilities subject to fire management (English summary). The law also defines the steps of design appraisal and acceptance testing of the installed systems.
For a tenant, the practical points remain: the building should have a fire design approval where required, installed systems should be accepted, and the real use should match the approved use. Which steps apply to your case depends on the building, its date and its size. Ask the authority.
The ways a building can lack approval
| Case | What it means |
|---|---|
| No approval at all | The design was never appraised, or papers are missing |
| Approval but no acceptance | The systems were not tested and accepted as built |
| Approval for another use | The papers cover storage; you plan production |
| Approval for a smaller area | The building was extended later |
| Old approval under earlier rules | May need updating; confirm treatment with the authority |
| Systems not working | Papers exist but alarm, pump or hydrants fail on site |
Each case has a different fix and a different delay.
What can go wrong
- Delay. You cannot open until the approval is complete. Rent may already run.
- Cost. Work to bring the building into line: pumps, tanks, alarm, walls, exits.
- Penalties and stoppage. The authorities can inspect and apply measures to a facility that does not comply. Penalty levels and procedures are set by the rules in force.
- Insurance. A claim after a fire can be disputed if the building lacks required approvals or the use differs from the papers. See tenant insurance.
- Customer audits. Buyers’ auditors ask for fire papers and drills. A gap can lose an order. See customer audit requirements.
- Other permits. Some registrations ask for fire compliance. A gap can hold them up.
- Safety. The most important point: people work in the building.
Checks before you sign
- Ask for the fire design approval and the acceptance record. Read the date, the stated use and the area.
- Walk the building with the papers. Compare layout, floors, partitions and exits.
- Test the alarm and look at the pump, tank and hydrants.
- Ask when systems were last tested and by whom.
- Ask the landlord what the unit was used for and whether the use ever changed.
- Describe your process in writing and ask a licensed consultant whether the approval covers it.
Our guides on fire approval and change of use give the detail. To find units whose papers already match, see factories with permits in place.
Lease clauses that protect you
| Clause | What it does |
|---|---|
| Landlord warranty | The landlord states the building has valid approval and acceptance for the agreed use |
| Condition precedent | The lease starts, or rent starts, only after the papers are delivered |
| Cure period | The landlord has a fixed time to fix gaps at its cost |
| Long-stop date | If not fixed by a set date, the tenant may leave |
| Refund | Deposit and advance rent returned in full on exit |
| Allocation of cost | Who pays for works the authority requires, split by cause: building defect or tenant change |
| Rent-free cover | Rent-free months cover the time needed for a tenant-driven approval |
See rent-free periods and early termination for how these are usually written.
Looking for a factory now? Send my requirements
If the gap is the tenant’s change
Sometimes the building is fine and your process creates the gap: higher fire load, tall racking, a paint booth or hazardous goods. Then the tenant normally applies and pays. Plan the time and cost in your start-up timeline. Ask the consultant for realistic ranges and add a margin.
What to do when you find a gap
- Write down the gap and take photos.
- Ask the landlord for its plan, cost and date, in writing.
- Ask your consultant how long the fix takes.
- Decide: fix before handover, rent-free cover, a lower rent or walk away.
- Do not start production, or move in expensive equipment, until the position is clear.
Common mistakes
- Taking a verbal assurance that “the papers are fine”.
- Reading the approval but not the acceptance.
- Assuming a former tenant’s use matches yours.
- Starting fit-out before approval, then having to change it.
- Not writing the remedy into the lease. See verbal promises.
Example: how a delay turns into a cost
This example is made up to show the arithmetic. A tenant signs a lease for a 2,000 m² unit at US$5.5 per m² per month, so rent is US$11,000 a month. The fire acceptance for part of the building is missing. The tenant learns this after fit-out begins. If completing it takes four months, the rent paid with no production is US$44,000, before the cost of idle staff, delayed orders and any penalty. If the lease had started rent only after delivery of the papers, the landlord would have carried that cost and had every reason to fix it quickly. The clause costs the tenant nothing to ask for and changes who feels the delay.
Questions for the fire authority or consultant
- Does the existing approval cover my process, my storage height and my layout?
- Which of my planned changes need a new or updated approval?
- What documents does the authority need, and who can file them?
- What is a realistic range for processing time in this area?
- What measures can apply while the approval is pending?
Ask in writing and keep the replies. Add the answers to your plan.
What not to do
- Do not start production to “test” the line while approval is open.
- Do not rely on a landlord’s friend at an office. Official answers are in writing.
- Do not hide a process change from the consultant to get a quick yes. The approval must match the real use.
- Do not skip the acceptance record because the sprinklers “look new”.
Related checks
Fire is one of several papers that can be missing. The same visit should cover land use (wrong land use), power, the building permit and the park’s rules. The ready-built factory checklist puts them in one list.
Get a shortlist
When we visit a factory we ask for the fire papers and note the approved use and any gap. Units with open fire questions are marked so you can decide before you travel. Send your requirements with your process, and we will reply within 24 business hours. Tenants pay nothing.
Frequently asked questions
Can I operate a factory in Vietnam without fire approval?
Not safely. Fire safety is a legal condition for buildings and facilities that the rules cover, and authorities can inspect, penalise and require operations to stop. Ask the fire authority or a licensed consultant about your case.
Who is responsible for the fire approval in a leased factory?
It depends on the lease. The landlord should deliver a building with approval and acceptance for the agreed use. If the tenant changes the use, the tenant often applies. Write it down.
How long does a fire approval take?
It depends on the project, the completeness of the file and the office. Do not rely on a promised date. Ask the authority and set a long-stop date in the lease.
Should I pay rent while the approval is pending?
Try to link the rent start date to the delivery of the approval. If the landlord will not agree, ask for a rent-free period that covers the expected time plus a margin.