How to Find a Vietnam Factory Whose Papers Already Match Your Use

November 21, 2026

You can shorten a start-up by choosing a factory whose approvals already cover your use. Most of the time that means fire design approval and acceptance, a completed building with a construction permit, the right land use purpose and a park that accepts your business line. The catch: papers cover a stated use. A building that is approved for warehouse storage does not automatically work for a paint line. The match between paper and process is what saves time.

This guide shows which approvals can sit in the building, which belong to your company, and how to shortlist units whose papers fit. Rules differ by case, so confirm with the authority or a licensed adviser.

Which approvals belong to what

Approval or status Held by Can it be ready before you arrive?
Land use right and land use purpose Landlord or park developer Yes, must be verified
Construction permit and completion Landlord Yes, for the building as built
Fire design approval and acceptance The building, for a stated use Yes, if the use matches yours
Park acceptance of the business line Park master plan and sector list Partly, the park still checks your project
Investment registration certificate Your company No, applied for in your name
Enterprise registration Your company No
Environmental documents Usually your project or company Partly, depends on scale and process
EPE status Your company, with customs No, but the site must allow it

The first three can be ready. The rest come after you have a unit and a plan. Read the sections below for how to test each.

Fire approval and acceptance

Fire safety is the most likely candidate for a ready-made approval. A new fire law took effect on 1 July 2025 (Law 55/2024/QH15) together with Decree 105/2025/ND-CP. A building completed earlier was approved under the rules of its time. Do not assume that an old approval is void, and do not assume it is enough. Ask the fire authority or a licensed consultant how it is treated for your use.

On site, check:

  1. The approval document, its date and the approved use.
  2. The acceptance record for the installed systems.
  3. Whether the area, floors and layout match the approved drawings.
  4. Whether your process raises the fire load or adds hazardous goods.

Our guides on fire approval and change of use go deeper. If a unit has no valid approval at all, read what that risk looks like before you go further.

Building permit and completion

Ask for the construction permit and the completion record. Compare the as-built building with the drawings. Extra floors, enclosed canopies and added offices may lack permits. A fit-out that adds a mezzanine can need a permit too, which is covered in our mezzanine guide.

Land and park

In an industrial park, the land use purpose is production and business, and the park has a master plan with allowed sectors. Ask for the land papers and the park confirmation that your business line is allowed. See business line fit and due diligence papers.

EPE: building and company

An export processing enterprise has its own customs regime. The status is granted to the company. The site matters because the area may need clear separation and the park must allow the activity. A unit that a previous EPE tenant used may already have a fenced area and a layout that suits customs supervision. That helps, but your company still goes through its own procedure. Read our guide to EPE requirements and ask your adviser whether you need it at all.

Environmental documents

Whether you need an environmental permit or an impact assessment depends on the scale and type of your project, not on the building alone. A landlord’s previous tenant may hold documents in its own name. They do not pass to you automatically. See environmental permits and the EIA guide.

How to shortlist units with matching papers

  1. Write your process down. Products, materials, hazardous goods, peak storage height, headcount, machines that produce heat or sparks.
  2. Ask each landlord for the approved use in the fire papers, before you ask for rent.
  3. Prefer units previously used for a similar process. A plastics plant moving into a former plastics plant meets fewer surprises than into a former garment plant.
  4. Compare paper with site during the visit.
  5. Ask who handles gaps. If the approval lacks acceptance for part of the building, the landlord should complete it before handover.
  6. Put it in the lease. The landlord confirms the papers cover the agreed use, and you get a right to leave if they do not.

Looking for a factory now? Send my requirements

When papers do not fit

You have three options: choose another unit, accept a new approval step and plan time for it, or change your layout to fit the existing papers. Each has a cost. A new approval step can add weeks or months, and the lease should say who applies, who pays and what happens if the authority refuses. Use the timeline guide to put the delay in your plan.

Questions to put to every landlord

  • What use is stated in the fire approval, and for which area?
  • Do you have the acceptance record for the installed systems?
  • Has the layout changed since the approval?
  • What was the unit last used for?
  • Who is responsible if the authority says the papers do not cover my use?

An example of paper against process

This is an example, not a real case. A tenant plans to run injection moulding with 6 m high racking for finished cartons. The landlord offers two units.

Unit A Unit B
Approved use in fire papers General storage, low rack height Light manufacturing and storage
Acceptance record Complete Complete for the main hall, missing for the office block
Last tenant Furniture trading Plastic parts
Likely gap for the tenant Higher fire load and racking may need a new approval Office block acceptance to be completed by the landlord

Unit B looks closer on paper. It still needs a lease clause that makes the landlord complete the acceptance of the office block before handover. Unit A could be the better building but adds an approval step to the plan. The point is to compare the gap in each unit, not to look only at the rent.

How much time a match can save

No one can promise a fixed number of weeks, because approval times depend on the case and the office. What you can do is list the steps for each unit and mark which are already done. Units with fewer open steps allow a shorter plan. Ask the landlord, the park and a consultant for realistic ranges and keep their answers. Treat any promise of a fixed date as a point to put into the lease with a remedy, not as a fact.

Older buildings

Older units may have approvals under earlier rules. This is not a reason to avoid them, because many are good buildings at fair rents. It means you should ask the fire authority or a licensed consultant whether the existing approval is still accepted for your use under the current rules, and whether any upgrade is expected. Include the answer in your cost plan. Also read our post on hidden defects in old factories.

Get a shortlist

When we visit a factory we ask for the fire papers and note the approved use next to your process. Units where the papers clearly do not fit are flagged, so you can decide before you travel. Send your requirements and include your process, and we will reply within 24 business hours. Tenants pay nothing.

Frequently asked questions

Can I rent a factory that already has EPE status?

EPE status is held by a company, not by a building. A unit can be suited to an EPE, for example inside a park that allows it, but your company applies in its own name. Ask the park and customs which conditions apply to your unit.

Does fire approval move with the building to a new tenant?

The approval and acceptance belong to the building for the use stated in them. If your process, layout or fire load differs, you may need a new or updated approval. Ask a licensed consultant or the fire authority.

Why do approvals reduce start-up time?

Each approval you do not need to apply for removes weeks or months from the plan. The saving is real only if the existing papers cover your intended use.

How do I prove a factory has valid approvals?

Ask for the documents, with dates and the approved use, and compare them with the building on site. Do not accept a verbal statement or a photo of one page.