What If the Power the Landlord Promised Does Not Arrive?
November 21, 2026
If the promised power does not arrive, you pay rent on a building you cannot run. The fix is to test the supply before you sign and to write power into the lease as a delivery obligation, with a date, an acceptance test, a rent break for delay and a right to leave. A line that says “power available” is not enough.
This guide is about the failure and the contract. For sizing your load, read the kVA guide. For the cost of a bigger transformer, read the transformer upgrade guide.
How the gap appears
Power problems rarely look like lies. They look like small differences between words.
- Installed versus available. A 1,000 kVA transformer may serve three units. Your share is not 1,000 kVA.
- Installed versus approved. The transformer may be bigger than the capacity the power company has approved for the connection.
- Today versus later. “We will upgrade it for you” can mean months of waiting for design, approval, equipment and installation.
- Capacity versus quality. The unit draws the load, but voltage dips, outages or poor power factor stop sensitive machines.
- Park versus unit. The park has spare power at its main substation, but the line to your unit is short.
- Verbal versus written. The landlord promised on a call and the lease says only “electricity supply as available”.
What the problem costs
A missing power supply delays production, but the costs start earlier.
| Cost | Why it happens |
|---|---|
| Rent while idle | Rent often starts at handover, not when you can run |
| Machines waiting | Imported equipment sits in the unit or in storage |
| Staff on payroll | Hired and trained workers have no line to run |
| Generator hire | A stopgap that costs fuel and may not carry the full load |
| Missed orders | Customer start dates slip, and penalties may follow |
A few weeks of delay can cost more than the whole difference in rent between two units. That is why the supply is worth checking early.
Test the power before you sign
- Read the nameplate. Photograph the transformer plate. Note kVA, voltage and the maker. Compare with what the landlord said.
- Ask who the transformer serves. One unit, several or the whole block. Ask for a single-line diagram.
- Ask for the supply contract or approved capacity. The electricity supply contract for the unit, or a document from the power company, shows what is approved. Compare it with the transformer.
- Look at bills. Ask for recent bills of the current tenant, with the maximum demand. If the current tenant never used more than a fraction of your need, that tells you little about what the supply can give. If it ran near the limit, that tells you more.
- Check the cables and panels. The main breaker, busbar and cables must carry your load, not only the transformer.
- Ask the park. The management board or the park’s power department can say whether spare capacity exists and how a new connection is handled.
- Ask for a supply confirmation before signing, in writing, from the party that supplies power. If the landlord cannot or will not obtain one, it is a signal.
- Test under load on handover if possible. See the handover report.
If you are unsure, ask your electrical contractor to join the visit. An hour on site can save months.
Words that cause trouble
| Landlord says | What to ask |
|---|---|
| “Power is no problem” | Which kVA, which voltage, dedicated or shared? |
| “We can upgrade easily” | Who applies, who pays, how many weeks, what if it fails? |
| “The park has plenty of power” | Is the capacity allocated to this unit in writing? |
| “Same as the last tenant” | What was its maximum demand and its contract capacity? |
| “Power will be ready by handover” | Where in the lease is that promise, and what happens if it is late? |
Looking for a factory now? Send my requirements
Clauses to write into the lease
Specification
State the capacity in kVA, the voltage, the phases and whether the supply is dedicated to your unit. Attach the single-line diagram.
Delivery date and acceptance
Set the date by which the power must be available at the unit’s main panel. Define how it is accepted: a test, a meter reading or a letter from the power company. Rent and the start of the term should link to this acceptance, not only to handover of the keys.
Remedies for delay
- Rent abatement. No rent, or a reduced rate, for each day of delay after the date.
- Extension of the rent-free period by the same number of days. See the rent-free period guide.
- Liquidated damages, if the landlord will accept them, as a fixed amount per week.
- Right to complete the works yourself and deduct the cost from rent, up to a cap.
- Exit right. If the power is not delivered by a long-stop date, you may end the lease and recover the deposit, advance rent and a stated share of the fit-out spent.
Cost and approvals
Say who applies to the power company, who pays the fees, the transformer and the cables, and who owns the equipment at the end. Cap the tenant’s share. Link the landlord’s duty to make reasonable efforts and to keep you informed.
Quality
Add a duty to keep the supply in good order and to repair faults on the landlord’s side of the meter within a stated time. For sensitive production, ask for the voltage tolerance in writing. See also backup power in the kVA guide.
If power is already late
- Write down the facts. Date, promise, current supply, the gap.
- Send a formal notice under the lease, citing the clause and the delay.
- Ask for a dated plan from the landlord and the power company.
- Keep records of cost. Rent paid, idle staff, generator hire, freight.
- Consider a temporary supply, such as a generator, and ask the landlord to share the cost.
- Escalate to the park management board, which may help move a stalled connection.
- Speak to your adviser before you withhold rent or end the lease. The right route depends on the clauses you signed. See dispute resolution.
Plan for the timing risk
Treat power as the longest item in your schedule. If you need a new connection or an upgrade, assume it takes months and not weeks. Start the request as early as the landlord allows. Do not order machines to arrive before the power date is firm. The timeline guide shows where power sits in the plan.
A short script for the landlord conversation
Use plain questions and ask for the answers by email.
- “What is the transformer rating, and does it serve only my unit?”
- “What capacity has the power company approved for this unit?”
- “What is the maximum demand shown on recent bills?”
- “If I need more, who applies, who pays and how many weeks does it take?”
- “Will you write the capacity and the delivery date into the lease?”
- “What happens to my rent and my term if the date is missed?”
A landlord who answers all six in writing has probably thought about the supply. A landlord who answers “no problem” to all of them has probably not.
Get a shortlist
For each unit we record the transformer rating, whether it is dedicated and what the owner can show about approved capacity, and we say when it could not be confirmed. Send your requirements with your kVA need and we reply within 24 business hours. Tenants pay nothing.
Frequently asked questions
Why does promised power not arrive?
Common causes are a transformer shared with other units, a rating on paper that is higher than the connection actually approved, a grid upgrade that has not been built and a landlord who counts spare capacity that is already allocated.
How do I prove how much power the unit can draw?
Ask for the transformer nameplate, the electricity supply contract or approved capacity for the unit and recent bills with maximum demand. Then ask for a load test or a supply confirmation from the utility before you sign.
What should the lease say about power?
State the capacity in kVA and voltage, whether it is dedicated, the delivery date, an acceptance test, a rent reduction for each month of delay and the right to end the lease and recover payments if the power is not delivered by a final date.
Who pays if the unit needs a bigger transformer?
It is a matter for negotiation. Settle it in the lease before signing, with a cost cap, a timeline and a rent start date linked to the power date.