How to Check the Fire Alarm, Hydrants and Water Supply Before You Lease
November 21, 2026
Test the fire alarm, look at the hydrants and read the pump records before you sign a lease, because these systems show whether the building is really ready for people to work in. A panel with no faults, a pump that starts and a hydrant that flows tell you more than any approval stamp. They also decide how much work you inherit.
This guide is general information, not engineering advice. A licensed fire consultant must check your case.
The standards in 2026
Several standards changed recently, so papers of different ages cite different ones.
| System | Current standard we found | Note |
|---|---|---|
| Fire alarm | TCVN 7568-14:2025 | Announced in May 2025. Replaced TCVN 7568-14:2015 and TCVN 5738:2021 |
| Hydrant pillars (equipment) | TCVN 6379:2024 | Replaced TCVN 6379:1998 |
| Sprinklers | TCVN 7336:2021 | See our sprinkler guide |
| Equipment and layout of fire protection means | TCVN 3890:2023 | Replaced TCVN 3890:2009 |
| Overall fire code | QCVN 06:2022/BXD and Amendment 1:2023 | See our QCVN 06 guide |
The alarm standard is listed as in force, with its replacement notes, in the national standards database. Sources disagree on the number of the announcing decision, so quote the standard number and not the decision number.
Which systems a building needs is not set by these standards. The fire code and the approved fire design decide that. The standards say how to design and install what the design requires. A building approved before May 2025 was probably designed with the older alarm standard, and that is normal. New works are assessed under current editions, so ask your consultant.
Fire alarm: what to see and test
An alarm system has detectors, manual call points, a control panel, sounders and often a link to other systems.
| Check | What good looks like |
|---|---|
| Control panel | Located in a staffed or visible place. Shows no standing faults or disabled zones |
| Zones | A zone plan beside the panel that matches the building |
| Detectors | Present across the hall, offices and equipment rooms, not covered, painted or removed |
| Call points | At exits and along escape routes, unobstructed |
| Sounders and lights | Audible in all areas, including noisy production |
| Power | Mains plus battery backup. Ask for the battery test date |
| Links | Sprinkler flow signals, door releases and smoke exhaust are connected where designed |
| Records | Acceptance record, test reports and a service contract |
Ask the landlord to trigger one detector or call point while you stand at the panel. Watch for a clear zone indication and for sounders in the far end of the unit. Do not touch the system yourself. A false alarm can bring a response and costs goodwill.
Noisy processes need attention. Heavy noise can drown sounders, and dust, steam, oil mist and welding fumes can set off or blind detectors. If your process makes any of these, tell the consultant, since detector type and placement may need to change.
Hydrants and hose points
There are three kinds of water point.
- Outdoor hydrants. Pillars in the park roads or on the plot. The hardware standard is TCVN 6379:2024.
- Indoor hydrants and hose cabinets. Points inside the building on the escape routes.
- Fire engine connection. A point where the fire service can feed the building system.
Check these on site:
- Count the hydrants near the building and compare them with the approved plan.
- Look at the condition of each: caps present, no rust, valves that turn, no blocked access.
- At indoor points, open the cabinet and confirm that the hose, nozzle and coupling are present and the same type.
- Ask for a flow and pressure test on a hydrant. The result should be written and dated.
- Check that fire engines can reach the hydrants over park roads, and that parking or stacking does not block them.
Pump, tank and water supply
Water is the part that fails most quietly. A good alarm and clean hydrants mean little if the supply is short.
- Source. Is the water from the park main, a ground tank or both? Ask what share of fire demand the park main covers.
- Tank. Check the size and the level. Ask what volume the approved design needs.
- Pumps. See the duty pump, a standby pump and the controller. Ask for the last run test and the fault log. The pumps should have a reliable power supply and a backup if the design requires one.
- Valves. Main valves should be in the open position and supervised.
- Papers. The water supply design, the acceptance record and the yearly test reports.
If the park supplies the water, ask the park management for its fire water arrangement and test records. Our infrastructure guide lists other park checks.
Looking for a factory now? Send my requirements
Extinguishers and signs
Portable extinguishers should be in the right place, in date, tagged and unobstructed. Emergency lights and exit signs should work on battery. These small items are cheap to fix, but their absence shows how the building has been looked after. Equipment and layout rules are in TCVN 3890:2023.
What changes when you move in
- Your fit-out can block detectors, hide call points or move walls. Re-plan the alarm zones after layout drawing.
- High racking or a mezzanine needs the alarm and hydrant layout rechecked.
- Extra buildings or new processes raise the water demand.
- A change of use may need a new design review. See change of use.
What to write into the lease
- The landlord confirms the systems have approval and acceptance and works at handover.
- A list of faults found on the handover report, with a date for repair.
- Who services each system, how often and who pays.
- Who keeps the test records.
- Access to the pump room and the panel for the tenant’s safety staff.
Use the handover condition report to record what you saw, with photos and dates.
A visit checklist
Print this and take it with you.
| Item | Seen | Notes |
|---|---|---|
| Alarm panel shows no faults | ||
| Zone plan matches the building | ||
| One detector or call point tested with the landlord | ||
| Sounders audible at the far end | ||
| Battery test date recorded | ||
| Outdoor hydrants counted against the plan | ||
| Indoor hose cabinets complete | ||
| Pump started and tank level read | ||
| Main valves open and supervised | ||
| Extinguishers in date | ||
| Emergency lights and exit signs working | ||
| Test records and acceptance record copied |
Photograph each item and keep the pictures with the handover report.
Gaps that turn up on checklists
- Panel in fault or zones disabled. Someone silenced a nuisance alarm and never restored it.
- Missing or covered detectors. Painted over, removed during repairs or hidden behind new ducts and ceilings.
- Flat batteries. The panel works on mains but fails when power is cut.
- Hydrants with no flow record. Nobody has opened them for years, or the park main has low pressure.
- Hose cabinets without hoses. Equipment taken for other uses.
- Pump that does not start. A pump without a recent run test is unproven until it has run.
- Blocked access. Stock, parked trucks or motorbikes in front of hydrants and fire doors.
Each item is a handover item. List it, put a date next to it and agree who fixes it. Ask the park, too. Find out whether it has a fire service plan, a drill programme and a contact at the local fire unit, and how long the fire service takes to reach the park.
Get a shortlist
We look at the alarm panel, the hydrants and the pump room at each visit and ask for the test records. Send your requirements and we reply within 24 business hours. Tenants pay nothing.
Frequently asked questions
Which standard covers fire alarms in Vietnam now?
TCVN 7568-14:2025 covers the design and installation of fire alarm systems in buildings. According to the national standards database it replaced TCVN 7568-14:2015 and TCVN 5738:2021. A building approved earlier was probably designed to the older standard.
Does an older alarm design make a building non-compliant?
Not by itself. A building keeps the approved design it was accepted under. New works, extensions and changes of use are assessed under the editions in force when you apply, so ask your consultant which edition applies.
What should I test on a visit?
Trigger a detector or a call point with the landlord present, watch the panel and the sounders, and check the hydrant and pump records. Do not test anything on your own without the landlord's agreement.
Who maintains the alarm and hydrant systems in a leased unit?
The lease must say. Often the landlord keeps the fixed systems and the tenant keeps its own extinguishers and the systems it adds. Agree who pays for yearly tests and repairs before you sign.