Guides / Standards
What ISO 14644 Cleanroom Classes Mean for a Factory Lease in Vietnam
November 21, 2026
A cleanroom class is a measured result, not a feature of a building. ISO 14644-1 defines the classes by the number of airborne particles in a cubic metre of air, from ISO Class 1 (cleanest) to ISO Class 9. The current edition is ISO 14644-1:2015, which replaced the 1999 edition. A factory can host a cleanroom, but it does not come with a class. The class comes from the cleanroom you build inside it and the test report that proves it.
This guide explains what the standard says, what the parts of the series do and what that means when you choose a unit. For the base-building checks of height, floor, roof, power and plant space, read our guide on cleanroom factories for rent. Here we focus on the standard itself.
The classes
ISO 14644-1 sets maximum particle concentrations for several particle sizes. At 0.5 micrometres, which is the size most electronics and medical device buyers quote, the limits for the classes you meet most often are:
| ISO class | Maximum particles per m³ at 0.5 µm or larger | Typical use |
|---|---|---|
| ISO 5 | 3,520 | Semiconductor steps, sterile filling zones, precision assembly |
| ISO 6 | 35,200 | Optics, sensitive assembly |
| ISO 7 | 352,000 | Medical device assembly, electronics, optics |
| ISO 8 | 3,520,000 | Packaging, general controlled assembly |
The Wikipedia article on cleanrooms shows the full table, and the standard itself is the final source. Each step down in class cuts the allowed count by a factor of ten.
A customer may write “Class 100,000” in a drawing. That is an older US Federal Standard 209E term, which was withdrawn in 2001 and replaced by ISO. Ask the customer to restate the requirement as an ISO class, because the particle sizes and test methods differ.
Three states of use
A room can be classified in three states, and the state matters because the same room has different counts depending on whether people and machines are active.
- As built. The room is complete and the services work, but no equipment or people are present.
- At rest. Equipment is installed and running as agreed, but no people are present.
- Operational. The room is in normal use with people and the process running.
The class on a certificate must name the state. A room that meets ISO 7 at rest may not meet it in operation. When a landlord says a unit “has an ISO 7 cleanroom”, ask for the report and read the state and the date.
The parts of the series
| Part | Subject | Use for a tenant |
|---|---|---|
| ISO 14644-1 | Classification by particle concentration | Defines the class you promise |
| ISO 14644-2 | Monitoring to show continued compliance | Sets how you keep proving the class |
| ISO 14644-3 | Test methods | Describes the tests the lab performs |
| ISO 14644-4 | Design, construction and start-up | Guides the cleanroom contractor |
Other parts cover areas such as operations. Editions of the later parts were updated in recent years, for example Part 4 in 2022. Ask your contractor which editions the project follows and write them into the contract.
Industries add their own rules on top. The EU GMP guide for sterile medicines, for instance, refers to ISO 14644-1 for particle counts and adds its own grades and monitoring. See GMP factory requirements for the pharmaceutical side.
The Vietnamese national series
Vietnam publishes cleanroom standards as the TCVN 8664 series, adopted from ISO 14644. Its Part 1, TCVN 8664-1:2011, is identical to the 1999 edition of ISO 14644-1, which has since been replaced. We could not confirm a newer national edition. Because international buyers audit to the current ISO text, treat TCVN as a local reference and let your customer’s contract decide which version applies.
What the standard means for the building
The standard gives no rule for the building, but the class sets the load on it.
| Target | What it asks of the base building |
|---|---|
| ISO 8 | Sealed envelope, filtered supply air, moderate power for air handling. Many standard shells can host it |
| ISO 7 | More air changes, tighter envelope, good floor flatness, enough power for air handling and chillers |
| ISO 6 and ISO 5 | Strong air supply, pressure control, low vibration, high power quality and space for large plant. Fewer sites suit this |
Several checks are common to all classes:
- Air tightness. A leaky shell loses pressure and brings in dust. Check roof joints, wall panels and door gaps.
- Power. Air handling and chillers run all day. See transformer size and kVA and electricity cost.
- Floor. Flat, dry and strong enough for the wall system and equipment. See floor load capacity.
- Plant space. Air handlers, chillers and cooling towers need roof, slab or yard space.
- Drains and water. Floor drains inside clean zones are normally avoided. Check where the existing ones are and where condensate can go.
- Dust outside. Roads, open yards and neighbours who produce dust all load your filters.
Looking for a factory now? Send my requirements
Test, certify, repeat
A classified room is tested when it is built and again at intervals. The standard sets the minimum intervals for each class, and your quality plan or customer may ask for more. Budget for tests every year and for retests after repairs, filter changes or layout changes. Ask the contractor for a quote that includes the first classification report and the test schedule.
In the lease, add a clause that lets you keep the cleanroom running through the rainy season, with prompt repairs of roof leaks. A small leak is a quality event in a cleanroom. See who pays for repairs.
Fire and permits
A cleanroom adds new rooms, new materials and new air paths. Check how that changes sprinklers, detectors and exits, and whether a new fire approval is needed. See fire safety change of use.
Questions for the landlord and the contractor
- What clear height, floor flatness and roof condition does the unit have?
- Is there space for the air handling and chillers, and a lifting route?
- What is the transformer size, and can it grow?
- Will the landlord consent to partitions, ducts and roof openings?
- Which edition of ISO 14644 does the contractor follow, and who tests?
- What must be removed at the end of the lease?
Reading a cleanroom claim in a listing
Words like “cleanroom ready”, “class 100k” or “ISO 7 room” appear in listings and broker messages. They mean very little until backed by papers. Use this short check.
| Claim | What to ask | Red flag |
|---|---|---|
| “ISO 7 room” | Classification report, state of use, date, testing body | No report, or a report that is years old |
| “Cleanroom ready” | Which parts exist: ceiling, filters, air handlers, pressure control | Only painted walls and a coated floor |
| “Class 100,000” | Which standard the class refers to | Old US term with no ISO equivalent stated |
| “Filtered air” | Filter grade, air change rate, who maintains them | No maintenance record |
If a unit already has a cleanroom, treat it as a used fit-out. Check the panels, the ceiling, the floor coating and the air handlers. Ask what the landlord will leave and whether the previous tenant’s class can be transferred. In most cases it cannot, because the class belongs to the room as tested and operated. You will need a new classification once you own the process.
Common mistakes
- Writing the class without the state. “ISO 7” is not enough. State at rest or operational.
- Forgetting retests. A room slips out of class when filters age or the layout changes.
- Choosing the class from habit. A cleaner class costs more to build and to run. Ask your customer for the real requirement.
- Ignoring gowning and flow. People, parts and waste need their own routes in and out.
- Underestimating the lease term. A cleanroom needs years of use to pay back. Match the lease term and break options to the investment.
Get a shortlist
Tell us the ISO class, the area and the total connected load including air handling. We check height, floor, roof and power on site before a unit reaches your shortlist. Send your requirements and we reply within 24 business hours. Tenants pay nothing.
Frequently asked questions
Which edition of ISO 14644-1 is current?
ISO 14644-1:2015, which replaced the 1999 edition. ISO's records show it was last reviewed and confirmed in 2021. Vietnam's national series TCVN 8664 was based on the 1999 edition, so customers usually audit to the ISO text.
Does Vietnam have its own cleanroom standard?
The national series is TCVN 8664, adopted from ISO 14644. Its Part 1 follows the 1999 edition. Ask your adviser and your customer which text the audit uses.
Who certifies a cleanroom?
An independent testing body measures particle counts and other tests, and issues a classification report. The room is only a classified cleanroom once that report exists for the stated state of use.
Can any ready-built factory host an ISO 7 room?
Many can, if height, floor, roof, power and plant space are enough. The building does not give the class. The cleanroom fit-out and its air system do.
Looking for a factory now?
Send your requirements. We reply within 24 business hours and shortlist up to 5 checked factories. No fee for tenants.
Send my requirements