Why a Ready-Built Factory Needs Heavy Fit-Out to Meet GMP in Vietnam

November 21, 2026

Pharmaceutical GMP is a quality system for how a product is made, tested and released. It is not a building standard, but it puts hard demands on the building. A ready-built factory in southern Vietnam is a steel shell with a floor, a roof and power. To reach GMP it needs rooms, air systems, utilities, drainage and finishes that are not there when you receive the keys. That is why most GMP projects are fit-out projects, not move-in projects.

This guide explains the legal frame, the building demands and the lease points. It is general information, not regulatory advice. A pharmaceutical regulatory consultant must confirm what applies to your product.

The Law on Pharmacy 2024 (Law 44/2024/QH15) came into force on 1 July 2025. Decree 163/2025/ND-CP gives detailed rules and replaced the earlier implementing decree. The Ministry of Health, through the Drug Administration of Vietnam, runs the GMP inspection and certification system. The Ministry’s circulars set out the technical GMP rules. The circular most often cited for GMP is Circular 35/2018/TT-BYT, amended by Circular 12/2022/TT-BYT. We found no replacement, but the 2024 law is new, so ask your adviser to confirm which circular applies now. The English text of Decree 163/2025/ND-CP is on LuatVietnam.

GMP codes follow international guides, with the WHO and PIC/S guides as the usual references. Your customer may also audit to EU or US rules. Ask which code governs each product and market before you design.

Medical devices work under a different decree. Decree 98/2021/ND-CP, amended since, asks the manufacturer’s quality system to comply with ISO 13485. A summary of the decree and the declaration steps is available from legal databases. Check the current text with a regulatory adviser, because medical device rules have been amended more than once.

Cosmetics, supplements and other health products have their own routes. Ask the authority for your category. We do not advise on product registration here.

Why a standard shell falls short

GMP asks for control of cross-contamination, mix-ups and environmental conditions. Each demand turns into a building feature.

GMP demand What it means in the building What a ready-built shell usually has
Separate zones and flows Rooms with airlocks, one-way flow for people and materials One open hall
Controlled air Filtered supply air, pressure differences between rooms, temperature and humidity control Natural ventilation or simple fans
Cleanable surfaces Smooth walls, ceilings and floors, sealed joints, coved corners Painted block or steel sheet, bare slab
Utilities of quality Purified water, clean compressed air, clean steam where needed Tap water and general air
Drainage control Traps, sanitary drains, no open channels in clean areas Industrial drains and gutters
Records and security Controlled areas for storage, quarantine and sampling Open warehouse space
Qualification Documented design, installation and testing of rooms and systems None

Room classes and particle counts follow the cleanroom standard. See our guide on ISO 14644 cleanroom classes. Many GMP rooms need classified areas, and EU sterile rules add their own grades.

The shell checks that matter most

Because the fit-out is heavy, the base building has to be right. You cannot fix a weak shell inside a GMP room.

  1. Height. Clean rooms, ceiling voids and air handling need height. See clear height.
  2. Floor. Flat, dry, strong and free from cracks. A moisture problem in the slab can wreck a resin floor.
  3. Roof. No leaks and enough strength for air handlers. See wind load and roof structure.
  4. Power. Air handling and chillers run all day, and many pharma sites want back-up power. See transformer upgrade.
  5. Water and drains. Supply for a purified water plant, and a wastewater route that fits the park limits. See wastewater discharge standards.
  6. Plant space. Room for chillers, air handlers, water systems and a generator.
  7. Standalone building. Shared walls and shared air paths make cross-contamination harder to control. See standalone versus shared.
  8. Neighbours. Dust and smoke from nearby units load your filters and may affect environmental monitoring.

Fire, environment and other approvals

A GMP fit-out changes the layout, adds materials and uses solvents and gases. That can trigger a new fire approval. See fire safety change of use. It also affects the environmental file, and many pharma processes need wastewater pre-treatment and hazardous waste handling. See the environmental permit and chemical storage requirements.

Looking for a factory now? Send my requirements

Timeline

GMP projects have a long chain: design, approvals, construction, equipment, qualification, validation, trial batches and inspection. Each step can take months, and the authority’s inspection comes late. We do not give a standard duration because scope varies widely. Ask your consultant for a plan and add a margin. Compare it with the general timeline in our guide on how long it takes to set up a factory.

Lease terms to agree before you start

  • Rent-free fit-out period. Make it long enough for design, build and qualification. See rent-free periods.
  • Consent to works. Walls, ceiling hangers, roof openings, new drains and plant on the roof or yard.
  • Term and break option. The fit-out is a large sunk cost. A short lease can waste it. Consider a longer term with a break option after the approval date.
  • End of lease. Say what the landlord expects you to remove. See reinstatement at lease end.
  • Delay protection. If approvals slip, rent should not start running at full price.

Is leasing the right route?

If your product needs a high class of clean room, a long approval chain and a large sunk investment, a built-to-suit building may fit better than converting a standard shell. See built-to-suit versus ready-built. For smaller or earlier-stage projects, a leased shell with a staged fit-out can be a sensible start.

What the authority and your customer look at

The inspection is not limited to the rooms. Inspectors and customer auditors look at the whole system. For the building side, expect questions on:

  • the site layout and the flow of people, materials and waste
  • the state of repair of floors, walls, ceilings and doors
  • pest control and the condition of the surroundings
  • the air system: filters, pressure differences and records of tests
  • water systems and their testing records
  • storage areas, including quarantine and cold storage where needed
  • utilities and back-up power
  • the documents that show the building was designed, built and tested as planned

Those documents are often called qualification records. They tie the building to the quality system. Without them, a good room has little value at inspection. Ask your consultant what the project needs, and plan who writes and keeps them.

Questions for the landlord

  • Does the unit have a standalone structure, or does it share walls and air with a neighbour?
  • What is the clear height, floor condition and roof condition?
  • How large is the transformer, and can it be increased?
  • Where can plant rooms, chillers and air handlers go?
  • Will the landlord consent to the full fit-out and to the end-of-lease terms?
  • What are the park’s rules on wastewater, odour and hazardous waste?
  • Has the unit been used for any process that may leave residues?

Common mistakes

  1. Believing “GMP-ready” in a listing. There is no such state without a qualified fit-out and an inspection. Ask for facts.
  2. Choosing the lowest rent. A cheap shell with a weak roof or slab can cost more to fix than a better unit costs in rent.
  3. Starting design before the product list is fixed. Dosage forms and containment needs change the layout.
  4. Short lease, big fit-out. The investment needs a term that lets it pay back.
  5. Treating the landlord as a bystander. Consent, access and coordination affect every step.

Get a shortlist

Tell us the product type, the room classes you expect and the connected load. We check height, floor, roof, power and the park rules on site before a unit reaches your shortlist. Send your requirements and we reply within 24 business hours. Tenants pay nothing.

Frequently asked questions

Which law governs pharmaceutical manufacturing in Vietnam?

The Law on Pharmacy 2024 (Law 44/2024/QH15), in force from 1 July 2025, with Decree 163/2025/ND-CP giving the detail. The Ministry of Health issues the GMP technical rules.

Can I start GMP construction in any ready-built factory?

Some units can host it, but few come close to GMP as built. Most need a full fit-out of rooms, air systems, utilities and drains, so the shell is judged on whether it can carry that work.

Does a medical device plant need GMP?

Vietnam's medical device rules ask the manufacturer's quality system to follow ISO 13485. That is a quality management standard rather than the drug GMP code. Check the current decree with a regulatory adviser.

How long does a GMP fit-out take?

It depends on scope. Design, build, qualification and inspection each take months. Plan the timeline with your consultant and ask for a long rent-free fit-out period.