Guides / Standards
What Does QCVN 06 Require From a Factory Building?
November 21, 2026
QCVN 06:2022/BXD is the national fire safety code for buildings and structures in Vietnam, and it is the document behind most factory fire approvals. For a factory it asks four things: how dangerous the process is, how the building resists fire, how people get out and how fire is kept from spreading. A tenant should know these four, because each one links to a question to put to the landlord.
This guide is general information, not legal or engineering advice. Confirm your case with a licensed fire consultant and the fire authority.
Which version is current
The code was issued by Circular 06/2022/TT-BXD of 30 November 2022 and took effect in January 2023. It replaced the 2021 edition. Amendment 1:2023 came with Circular 09/2023/TT-BXD of 16 October 2023 and took effect on 1 December 2023. It changes some provisions only, and everything it does not mention stays as in the 2022 text. It also lets provinces issue local technical regulations in some cases.
The amendment has a transition rule. A design approved before 1 December 2023 continues under that approved design. A file not yet approved at that date follows the 2022 code together with the amendment. We found no later amendment in the sources we checked, so ask your consultant to confirm the status when you start.
Two other points keep readers out of trouble.
- The code is not the approval. Under the fire law (Law 55/2024/QH15) and Decree 105/2025/ND-CP, the fire authority reviews the design and accepts the finished works. QCVN 06 is the yardstick for the review. See our guide to fire approval.
- The code does not cover everything. The Ministry of Construction has said that some special buildings, such as petroleum and gas storage, fall under other rules. A tenant with a chemical or fuel process should expect separate requirements. See chemical storage.
How the code looks at a factory
1. Hazard class of the rooms and building
The code sorts production and storage rooms by explosion and fire hazard. The classes are A and B for explosion and fire hazard, C1 to C4 for combustible materials by fire load, D for non-combustible materials handled hot and E for non-combustible materials handled cold. The building then takes a class from the rooms inside it. Annex C holds the rules. Most other requirements depend on this class, so it is the first thing to settle. Our hazard class guide explains it for tenants.
2. Fire resistance of the building
The structure must resist fire for a time that depends on the building’s use, size and hazard class. This sets what the columns, beams, roof and walls must be made of and how they are protected. A steel frame that is fine for one class may need protection for another. Ask what degree of fire resistance the building was designed for and what the roof and wall panels are made of. Insulated panels differ in how their cores react to fire, and the approval should state the panel type.
3. Fire compartments and separation
Large production halls are divided into compartments by fire walls, fire doors and sealed openings. The permitted size of a compartment depends on the hazard class and the building’s fire resistance. The code also sets the distance between buildings and the access for fire engines. When you walk a unit, look for the fire walls in the drawings and check that someone has not cut new doors or pipe openings through them.
4. Escape routes
Escape rules look at the number of exits, their width and the distance from a workstation to an exit. The allowed distance depends on the hazard class and the number of people per square metre. The code also restricts which door types count as exits. Roller shutters and revolving doors do not count in the usual way, so ask your consultant how they are treated. It also asks for escape lighting, signs and smoke control on routes. Racking, new partitions and a mezzanine can lengthen the route or block an exit, so recheck the plan after your layout is drawn.
What this means for a tenant
| Code topic | Question for the landlord | Question for your consultant |
|---|---|---|
| Hazard class | Which class was the building approved for? | Which class is each of my rooms? |
| Fire resistance | What is the rated structure and the panel type? | Does my process need more protection? |
| Compartments | Where are the fire walls and doors? | Does my layout cross a compartment? |
| Escape | How many exits and what widths? | Do racking and partitions keep the routes legal? |
| Systems | Which alarm, sprinkler and hydrant systems were approved? | Are they sized for my storage? |
Looking for a factory now? Send my requirements
Where tenants run into trouble
- Approved for storage, used for production. The papers show a low hazard class and a light use. Heat, solvents or stock then raise the class.
- Layout drift. Earlier tenants added offices or mezzanines without updating the file.
- High racking. Tall storage changes sprinkler needs and can block escape routes. See the sprinkler guide.
- Missing acceptance. A design approval exists, but no acceptance record for the installed systems.
- Changed process after signing. The tenant adds a line that was not in the plan given to the landlord.
The cure is the same each time. Describe your process, materials and storage heights in writing before you sign, and ask the landlord to confirm in the lease that the building is approved for them. Put the cost and the deadline for any new approval in the lease too. Our guide to change of use covers the lease clauses.
Where to read the text
The code text, with Amendment 1:2023, is on a Vietnamese legal database. It is in Vietnamese. A fire consultant can mark the parts that matter for your plant, and that is cheaper than reading all of it. For the standards on alarms, sprinklers and hydrants that the code points to, see our guides on fire alarms and hydrants and sprinklers.
A short plan for a tenant
Fire rules can feel heavy, but the work for a tenant follows a clear order.
- Write the process sheet. Steps, materials, quantities, storage heights, number of people and any hot work.
- Collect the building file. Design approval, approved drawings, acceptance record and any later changes.
- Compare. Put the sheet next to the file. Mark every item where your use is heavier than the approved one.
- Take the gaps to a consultant. Ask what changes are needed, how long a new review takes and what it costs.
- Decide on the unit. Pick another unit if the gaps are large. If the landlord will carry out the works, get dates and costs into the lease.
Materials and the building envelope
The code also looks at what the building is made of. Wall and roof panels, ceilings, insulation and floor finishes all have fire behaviour. Sandwich panels are common in ready-built factories, and the panel core affects how fire spreads. Ask which panel was used, where it sits and whether the approval names it. If you plan to add partitions or an office inside the hall, tell your consultant the materials, because they must fit the approved design as well.
Get a shortlist
We ask for the fire design approval and acceptance record at every visit and compare the approved use with your process before a unit goes on your shortlist. Send your requirements and we reply within 24 business hours. Tenants pay nothing.
Frequently asked questions
What is QCVN 06 and which version is current?
QCVN 06 is the national technical regulation on fire safety for buildings and structures. The current text is QCVN 06:2022/BXD, issued by Circular 06/2022/TT-BXD, with Amendment 1:2023 issued by Circular 09/2023/TT-BXD. We found no later amendment, but confirm before you rely on it.
Does QCVN 06 give a fire approval to the building?
No. QCVN 06 is the technical code. The approval and acceptance come from the fire authority under the fire law and its decree. A building can follow the code on paper and still lack the approval documents.
What happens to a building approved under an older version?
Amendment 1:2023 says designs already approved before 1 December 2023 continue under the approved design. New designs and new works are assessed under the current text, so ask your consultant which version applies to your changes.
Can a tenant use a factory for a different purpose than the approval states?
Not without checking. A different process, higher fire load or new mezzanine can mean the approved design no longer fits. The fire authority decides, so ask a licensed fire consultant before you commit.