Is the Lightning Protection and Earthing in a Leased Factory Safe?

November 21, 2026

Three documents cover most of what a tenant needs to know here. TCVN 9385:2012 is the national guide for designing, inspecting and maintaining lightning protection on buildings. TCVN 9358:2012 covers the earthing system for equipment in industrial buildings. QCVN 25:2025/BCT is the current national technical regulation on electrical safety. It was issued with Circular 41/2025/TT-BCT and has applied since 8 August 2025, replacing QCVN 01:2020/BCT.

You do not need to read them cover to cover. You need to know what to ask the landlord, what to test before you move in and who pays for it. This guide is general information, not engineering or legal advice. Your electrical engineer and the park management board have the final word.

What each document does

Document What it covers Why a tenant cares
TCVN 9385:2012 Design, inspection and maintenance of lightning protection for buildings Tells you what a proper system includes and that it needs inspection
TCVN 9358:2012 Earthing of electrical equipment in industrial buildings Applies to your machines, panels and metal frames
QCVN 25:2025/BCT Electrical safety requirements Sets the safety baseline for installations and work around live equipment

TCVN 9385:2012 was adapted from a British standard of 1999. The IEC 62305 series is the international reference, and parts of it have been revised again in recent years. A Vietnamese design may follow the national guide while a European or American customer asks for IEC. Ask your customer which one the audit uses, and check that the building system can show compliance with it.

Standards change. Before you rely on any code number, ask your electrical adviser to confirm the current version. The record of QCVN 25:2025/BCT is on LuatVietnam.

Why this matters in southern Vietnam

The south has a long rainy season with frequent thunderstorms. A large single-storey steel factory is a tall metal object on flat ground. A strike can damage the roof, the electrical room, the control systems and the machines, and it can start a fire. Surges also travel along cables from outside the site, so a unit with good rods on the roof can still lose equipment through the power line.

A lightning event is a risk for people as well. Metal crane rails, roof ladders and exposed ducts all need a safe path to earth.

What a sound lightning system includes

You do not design this yourself, but you can see whether the pieces exist.

  1. Air termination. Rods, conductors or a bonded metal roof that take the strike.
  2. Down conductors. Routes from the roof to the ground, usually along columns or the outside wall.
  3. Earth electrodes. Rods or a ring in the ground, with test points that can be opened for measurement.
  4. Equipotential bonding. Metal parts such as crane rails, pipes and cable trays bonded together so there is no dangerous voltage between them.
  5. Surge protection. Devices at the main switchboard and at sensitive panels, so a surge on the line does not reach your equipment.

Ask the landlord for the design drawing or the as-built drawing of this system. Walk the roof edge and the outside walls and look for conductors, clamps and test boxes. Rust, loose clamps, cut conductors and missing covers all tell you the system has not been looked after.

Earthing and electrical safety inside the unit

Earthing is what keeps a fault from turning a machine frame into a live surface. It is also the basis for protective devices to trip.

Check these items on the visit:

  • Main earth bar in the electrical room, clearly labelled and connected.
  • Earth test report for the electrodes, with a date and the name of the testing body.
  • Residual current protection on circuits that feed portable tools and wet areas.
  • Panel condition: labels, closed covers, no burn marks, cable entries sealed.
  • Transformer room: access control, ventilation, fire separation and no storage inside.
  • Insulation and thermal checks of the main cables and busbars, if the landlord has done them.

Do not accept a verbal “it is all fine”. Ask for the test report. If the last one is old, or there is none, price an independent test into your move-in budget and ask the landlord to cover it or to fix the faults it finds. We do not quote test limits here. The standard and your electrical adviser set the pass value for your site. Our guide on reading the transformer plate and kVA explains what to check on the supply side.

Who is responsible for what

Item Usually the landlord Usually the tenant
Roof lightning protection and down conductors Yes Not unless the lease says so
Earth electrodes of the building Yes Test access and reporting of faults
Main switchboard and transformer Yes, if part of the base building Own sub-panels and distribution
Machine earthing and bonding No Yes
Rooftop add-ons: solar, fans, ducts Consent only Design, install, bond and test
Periodic testing Agree in the lease Agree in the lease

The point of the table is to find gaps. In many leases nobody owns the periodic test. Write down who tests, how often and who pays. Our post on who pays for repairs shows how to word that clause.

Looking for a factory now? Send my requirements

Rooftop equipment changes the picture

Solar panels, large fans and ducts all become part of the roof. They need to be bonded to the lightning system or protected by it, and they change the surge path. Get a written design from the installer, consent from the landlord and a test after the work. See our guides on wind load and roof structure and fire safety approval for the other checks that apply to roof works.

Audits and insurance

Customer audits and insurers often ask for the lightning protection test report and the electrical inspection records. A missing report can hold up an audit even when the system is sound. Our guide on what customer audits check in the building lists the other papers to keep ready. Your insurer may also ask about it. See tenant insurance.

Questions for the landlord

  • Can I see the lightning protection design or as-built drawing?
  • When were the earth electrodes last tested, and by whom?
  • Is there surge protection at the main switchboard?
  • Who tests and maintains the system during my lease?
  • May I add rooftop equipment, and who approves the bonding?
  • Have there been any lightning strikes or surge damage in this unit?

A move-in test plan

Do the checks in a sensible order so you do not pay twice.

  1. Before signing: ask for the drawings, the earth test report and the date of the last electrical inspection. Walk the roof edge and the electrical room.
  2. Before handover: ask the landlord to fix visible faults, such as loose clamps, missing covers and rust at the earth test boxes. Record the condition in the handover report.
  3. After handover and before power-up of your plant: have a licensed electrical contractor test earthing, insulation and protective devices on your own distribution boards and machines.
  4. After any rooftop or major electrical work: test again and keep the report with the drawings.
  5. Every year or at the interval your adviser sets: retest the lightning system and the earth electrodes, and record who did it.

Keep all reports in one folder on site. When an insurer, an auditor or the park asks, you can answer on the same day.

Common gaps

  • The lightning system exists on paper but the down conductors were cut during a roof repair.
  • Earth test boxes are buried under a concrete patch or full of water.
  • Surge protection is fitted at the main board but not at the sub-panel that feeds the control systems.
  • Crane rails and cable trays are not bonded into the earthing system.
  • A new tenant adds a rooftop unit and the old one is never re-tested.

Each of these is cheap to fix when found early and costly after a storm.

Get a shortlist

Tell us your load, your equipment and any rooftop plans. We look at the electrical room, the roof edge and the papers on site before a unit reaches your shortlist. Send your requirements and we reply within 24 business hours. Tenants pay nothing.

Frequently asked questions

Which standard covers lightning protection for a factory in Vietnam?

TCVN 9385:2012 is the national guide for the design, inspection and maintenance of lightning protection on buildings. Many international customers also expect the IEC 62305 series, so ask which one your customer audits against.

What is the current electrical safety regulation?

QCVN 25:2025/BCT, issued with Circular 41/2025/TT-BCT and effective from 8 August 2025. It replaced QCVN 01:2020/BCT.

Who looks after lightning protection in a leased unit?

The landlord normally provides the building system, and the tenant is responsible for what it adds, such as rooftop equipment and machine earthing. Write the split and the test schedule into the lease.

What record should I ask the landlord for?

The lightning protection design or as-built drawing and the latest test report for the earth electrodes. A unit that cannot show either needs an independent test before you move in.